OAR 690-020-0400
Emergency Action Plans (EAP)


(1)

An owner of a High Hazard Dam shall develop an Emergency Action Plan (EAP) consistent with this section. The EAP is to assist the Dam owner and local emergency management personnel to ensure human safety in the event of a potential or actual Dam Failure.

(2)

For new Dams or to increase the Dam Height of High Hazard Dams, the EAP is required to be submitted as part of the plans and specifications in OAR 690-020-0035 (Minimum Engineering Requirements for Final Design of New Dams or to Increase Dam Height) and OAR 690-020-0080 (New Dams, or to Increase Dam Height, Written Approval by State Engineer)(1), prior to commencing new Dam construction.

(3)

Owners of Dams which have been reclassified to a High Hazard Rating will be required to develop and submit an EAP within one year of being notified of the reclassification by the Department.

(4)

An EAP shall contain, at a minimum, the following key elements:

(a)

Means for emergency condition detection;

(b)

Means for emergency level determination;

(c)

Identification of, and information necessary for, notification and communication to be made at each level of emergency condition, including, but not limited to, contact information required in OAR 690-020-0180 (Requirement of Owners to Provide Contact and Transfer of Title Information)(1);

(d)

Description of actions to prevent a Dam Failure incident or to help reduce the effects of a Dam Failure and facilitate response to an emergency;

(e)

A map of Dam Failure inundation zones developed using a Dam breach inundation analysis for varying conditions as specified by the Department, including, but not limited to, dry weather conditions and high flood conditions. The Department may require one inundation map if the dry weather and high flood flows are not substantially different. The inundation mapping must include cross sections at locations of concern, and a description of expected depth and velocity of maximum breach flows at each cross section; and

(f)

Procedures for termination of the emergency.

(5)

The Dam owner shall file copies of the EAP with the Department, the Office of Emergency Management, and the local emergency services agency for the county where the Dam is located.

(6)

The Department will, in consultation with the local Office of Emergency Management:

(a)

Periodically review the EAP and may require updates to the plan that recognize the actual capabilities of the local emergency managers; and

(b)

Determine the appropriate frequency for conducting emergency response exercises.

Source: Rule 690-020-0400 — Emergency Action Plans (EAP), https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=690-020-0400.

690‑020‑0000
Purpose and Applicability
690‑020‑0022
Definitions
690‑020‑0024
General Department Authorities and Intergovernmental Coordination
690‑020‑0026
Fees
690‑020‑0028
Preliminary Plans and Specifications for Construction of New Dams or to Increase Dam Height
690‑020‑0035
Minimum Engineering Requirements for Final Design of New Dams or to Increase Dam Height
690‑020‑0036
Design Requirements for New Dams or to Increase Dam Height: Site Suitability and Geotechnical Evaluation
690‑020‑0037
Design Requirements for New Dams or to Increase Dam Height: Hydrology and Inflow Design Flood
690‑020‑0038
Design Requirements for New Dams or to Increase Dam Height: Embankment Dam Structures
690‑020‑0041
Design Requirements for New Dams or to Increase Dam Height: Concrete Dam Structures
690‑020‑0042
Minimum Design Requirements for New Dams or to Increase Dam Height: Spillways
690‑020‑0043
Design Requirements for New Dams or to Increase Dam Height: Penetrating Conduit(s) and Control of Flow through Conduits
690‑020‑0044
Design Requirements for New Dams or to Increase Dam Height: Instrumentation for Monitoring
690‑020‑0047
Design Requirements for New Dams or to Increase Dam Height: Geosynthetics
690‑020‑0048
Exceptions to Standard Design Requirements
690‑020‑0055
Design Requirements for New Dams or to Increase Dam Height: Design Drawings
690‑020‑0060
Design Requirements for New Dams or to Increase Dam Height: Construction Specifications
690‑020‑0065
Plan Requirements for New Dams or to Increase Dam Height: Construction Administration
690‑020‑0068
Plan Requirements for New Dams or to Increase Dam Height: Operations and Maintenance Plan
690‑020‑0070
New Dams or to Increase Dam Height: Submittals and Notifications by the Engineer of Record
690‑020‑0080
New Dams, or to Increase Dam Height, Written Approval by State Engineer
690‑020‑0100
Hazard Rating of Dams
690‑020‑0120
Dam Breach Inundation Analysis
690‑020‑0140
Modification of Dams
690‑020‑0160
Removal
690‑020‑0180
Requirement of Owners to Provide Contact and Transfer of Title Information
690‑020‑0250
Maintenance of Dams
690‑020‑0260
Inspection of Dams
690‑020‑0310
Requirement to Address Maintenance Actions Need for High or Significant Hazard Dams
690‑020‑0340
Potentially Unsafe or Unsafe Conditions
690‑020‑0400
Emergency Action Plans (EAP)
690‑020‑0420
Immediate Action to Prevent Dam Failure
690‑020‑0460
Proposed Final Order, Request for Hearing, Contested Case Process
690‑020‑0600
Civil Penalty Assessment for Dam Safety
Last Updated

Jun. 8, 2021

Rule 690-020-0400’s source at or​.us