OAR 839-025-0020
Public Works Contracts and Contract Specifications; Required Conditions


(1)

For purposes of this rule:

(a)

“Construction Manager/General Contractor contract” (or “CM/GC contract”) means a contract that typically results in a general contractor/construction manager initially undertaking various pre-construction tasks that may include, but are not limited to: design phase development, constructability reviews, value engineering, scheduling, and cost estimating, and in which a guaranteed maximum price for completion of construction-type work is typically established by amendment of the initial contract, after the pre-construction tasks are complete or substantially complete. “CM/GC” refers to the general contractor/construction manager under this form of contract. Following the design phase, the CM/GC may then act as a General Contractor and begin the subcontracting process. The CM/GC typically coordinates and manages the construction process, provides contractor expertise, and acts as a member of the project team.

(b)

“Construction specifications” include the detailed description of physical characteristics of the improvement, design details, technical descriptions of the method and manner of doing the work, quantities or qualities of any materials required to be furnished, descriptions of dimensions, required units of measurement, composition or manufacturer, and descriptions of any quality, performance, or acceptance requirements.

(2)

Every public works contract must contain the following:

(a)

A condition or clause that, if the contractor fails, neglects, or refuses to make prompt payment of any claim for labor or services furnished to the contractor or a subcontractor by any person, or the assignee of the person, in connection with the public works contract as such claim becomes due, the proper officer or officers of the public agency may pay such claim and charge the amount of the payment against funds due or to become due the contractor by reason of the contract (Reference: ORS 279C.515 (Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints));

(b)

A condition that no person will be employed for more than 10 hours in any one day, or 40 hours in any one week except in cases of necessity, emergency, or where the public policy absolutely requires it, and in such cases the person so employed must be paid at least time and one-half the regular rate of pay for all time worked:

(A)

For all overtime in excess of eight hours a day or 40 hours in any one week when the work week is five consecutive days, Monday through Friday; or

(B)

For all overtime in excess of 10 hours a day or 40 hours in any one week when the work week if four consecutive days, Monday through Friday; and

(C)

For all work performed on Saturday and on any legal holiday specified in ORS 279C.540 (Maximum hours of labor on public contracts) (Reference: ORS 279C.520 (Condition concerning hours of labor)(1));

(c)

A condition that an employer must give notice to employees who work on a public works contract in writing, either at the time of hire or before commencement of work on the contract, or by posting a notice in a location frequented by employees, of the number of hours per day and days per week that the employees may be required to work (Reference: ORS 279C.520 (Condition concerning hours of labor)(2)); and

(d)

A condition that the contractor must promptly, as due, make payment to any person, co-partnership, association or corporation, furnishing medical, surgical and hospital care or other needed care and attention, incident to sickness or injury, to employees of such contractor, of all sums which the contractor agrees to pay for such services and all moneys and sums which the contractor collected or deducted from the wages of the contractor’s employees pursuant to any law, contract or agreement for the purpose of providing or paying for such service (Reference: ORS 279C.530 (Condition concerning payment for medical care and providing workers’ compensation)).

(3)

Every public works contract that a public agency awards must contain a condition or clause that requires the contractor to:

(a)

Have a public works bond filed with the Construction Contractors Board before starting work on the project, unless the contractor is exempt under ORS 279C.836 (Public works bond)(4), (7), (8) or (9).

(b)

Require, in every subcontract, that the subcontractor have a public works bond filed with the Construction Contractors Board before starting work on the project, unless the subcontractor is exempt under ORS 279C.836 (Public works bond)(4), (7), (8) or (9).

(4)

Every subcontract that a contractor or subcontractor awards in connection with a public works contract between a contractor and a public agency must require any subcontractor to have a public works bond filed with the Construction Contractors Board before starting work on the public works projects, unless the subcontractor is exempt under ORS 279C.836 (Public works bond) (4), (7), (8), or (9).

(5)

Intentionally left blank —Ed.

(a)

Every public works contract and subcontract must provide that each worker the contractor, subcontractor or other person who is a party to the contract uses in performing all or part of the contract, must be paid not less than the applicable prevailing rate of wage for each trade or occupation as defined by the Commissioner of the Bureau of Labor and Industries in the applicable publication entitled Definitions of Covered Occupations for Public Works Contracts in Oregon.

(b)

If a public works project is subject to both ORS 279C.800 (Definitions for ORS 279C.800 to 279C.870) to ORS 279C.870 (Civil action to enforce payment of prevailing rates of wage) and to the Davis-Bacon Act (40 U.S.C. 3141 et seq.), every public works contract and subcontract must provide that the worker whom the contractor, subcontractor or other person who is a party to the contract uses in performing all or part of the contract, must be paid not less than the higher of the applicable state prevailing rate of wage for each trade or occupation as defined by the Commissioner of the Bureau of Labor and Industries in the applicable publication entitled Definitions of Covered Occupations for Public Works Contracts in Oregon or federal prevailing rate of wage.

(6)

Intentionally left blank —Ed.

(a)

The specifications for every public works contract must contain a provision that states the existing state prevailing rate of wage and, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act (40 U.S.C. 3141 et seq.).

(b)

Except as provided in subsection (d) of this section and sections (8) and (9) of this rule, the existing state prevailing rate of wage and the applicable publication entitled Definitions of Covered Occupations for Public Works Contracts in Oregon are those in effect at the time the initial specifications were first advertised for bid solicitations.

(c)

If a public agency is required under subsection (a) of this section or section (8) of this rule to include the state and federal prevailing rates of wage in the specifications for a contract for public works, the public agency shall also include in the specifications the requirement that the contractor pay the higher of the applicable state or federal prevailing rate of wage to all workers on the public works project.

(d)

Pursuant to ORS 279C.838 (Applicability of state and federal rates of wage)(4) and notwithstanding ORS 279C.830 (Provisions concerning prevailing rate of wage in specifications, contracts and subcontracts)(1), if the contract is subject to both ORS 279C.800 (Definitions for ORS 279C.800 to 279C.870) to 279C.870 (Civil action to enforce payment of prevailing rates of wage) and the Davis Bacon Act (40 U.S.C. 3141 et seq.), the public agency may provide in the specifications for the contract a single date to be used to establish the “existing state prevailing rate of wage,” the applicable publication entitled Definitions of Covered Occupations for Public Works Contracts in Oregon, and the “applicable federal prevailing rate of wage” that is consistent with the federal requirements under 29 CFR 1.6.

(e)

The specifications for a contract for public works must provide that the contractor and every subcontractor must have a public works bond filed with the Construction Contractors Board before starting work on the project, unless the contractor or subcontractor is exempt under ORS 279C.836 (Public works bond)(4), (7), (8) or (9).

(7)

Intentionally left blank —Ed.

(a)

The provisions described in sections (5) and (6), and sections (8) and (9) if applicable, must be included in all specifications for each contract awarded on the project, regardless of the price of any individual contract, so long as the combined price of all contracts awarded on the project is $50,000 or more (Reference: ORS 279C.830 (Provisions concerning prevailing rate of wage in specifications, contracts and subcontracts)).

(b)

A statement incorporating the applicable state prevailing wage rate publication and any amendments thereto into the specifications by reference will satisfy these requirements. Except as provided in subsection (c), such reference must include the title of the applicable wage rates publication or determination and the date of the publication or determination as well as the date of any applicable amendments.

(c)

When the prevailing wage rates are available electronically or are accessible on the Internet, the rates may be incorporated into the specifications by referring to the electronically accessible or Internet-accessible rates and by providing adequate information about how to access the rates. Such reference must include the title of the applicable wage rates publication or determination and the date of the publication or determination as well as the date of any applicable amendments. The reference requirements of this subsection will be satisfied if such reference includes Uniform Resource Locator (URL) information for a webpage or webpages showing the title of each applicable wage rates publication or determination and the date of each publication or determination as well as the date of any applicable amendments.

(8)

Intentionally left blank —Ed.

(a)

When a public agency is a party to a CM/GC contract, the CM/GC contract becomes a public works contract either when the contract first constitutes a binding and enforceable obligation on the part of the CM/GC to perform or arrange for the performance of construction, reconstruction, major renovation or painting of an improvement that is a public works or when the CM/GC contract enters the construction phase, whichever occurs first.

(b)

For example, the CM/GC will have a binding and enforceable obligation to perform or arrange for the performance of construction, reconstruction, major renovation or painting of an improvement after the public agency and CM/GC commit to the guaranteed maximum price.

(c)

For purposes of this rule, the CM/GC contract enters the construction phase when the agency first authorizes the performance of early construction, reconstruction, major renovation or painting work directly related to the improvement project.

(d)

The publication entitled Definitions of Covered Occupations for Public Works Contracts in Oregon and the prevailing wage rate in effect at the time the CM/GC contract becomes a public works contract shall apply and the applicable prevailing wage rates must be included with the construction specifications for the CM/GC contract.

(9)

A public works project described in ORS 279C.800 (Definitions for ORS 279C.800 to 279C.870)(6)(a)(B), (C), (D), or (E) that is not a CM/GC contract subject to section (8) of this rule, and for which no public agency awards a contract to a contractor for the project, is subject to the publication entitled Definitions of Covered Occupations for Public Works Contracts in Oregon and the existing state prevailing rate of wage or, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act that are in effect at the time a public agency enters into an agreement with a private entity for the project. (Note: The effective date of the applicable federal prevailing rate of wage may be different under federal law.) After that time, the specifications for any contract for the public works shall include the applicable prevailing rate of wage.

(10)

If a project is a public works of the type described in ORS 279C.800 (Definitions for ORS 279C.800 to 279C.870)(6)(a)(B), (C), (D), or (E), and no public agency awards a contract to a contractor for the project, a public agency will be deemed to have complied with the provisions of ORS 279C.830 (Provisions concerning prevailing rate of wage in specifications, contracts and subcontracts) if the public agency requires compliance with the provisions of section (7) of this rule in any agreement entered into by the public agency committing to provide funds for the project, to occupy or use the completed project, or authorizing the construction or installation of a solar radiation device.

(11)

Public agencies may obtain, without cost, a copy of the existing state prevailing rate of wages for use in preparing the contract specifications by contacting the Prevailing Wage Rate Unit or any office of the bureau.

Source: Rule 839-025-0020 — Public Works Contracts and Contract Specifications; Required Conditions, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=839-025-0020.

839‑025‑0000
Notice of Proposed Rules
839‑025‑0003
Forms
839‑025‑0004
Definitions Generally
839‑025‑0005
Purpose and Procedure for Determination Requests
839‑025‑0006
Purpose and Procedure for Addition of Trade
839‑025‑0007
Purpose and Procedure for Special Wage Determination
839‑025‑0008
List of Planned Public Improvements and Cost Analysis
839‑025‑0010
Payroll and Certified Statement Requirements
839‑025‑0013
Notice of Public Works Form
839‑025‑0015
Public Works Bonds Requirements
839‑025‑0020
Public Works Contracts and Contract Specifications
839‑025‑0025
Required Records
839‑025‑0030
Records Availability
839‑025‑0033
Posting Requirements
839‑025‑0034
Establishing a Work Schedule
839‑025‑0035
Payment of Prevailing Rate of Wage
839‑025‑0037
Residential Construction Projects
839‑025‑0038
Use of Multiple Wage Rate Determinations on Projects
839‑025‑0040
Payment of Fringe Benefits
839‑025‑0043
Frequency of Payment of Fringe Benefits
839‑025‑0045
Youth Apprentices
839‑025‑0050
Overtime Wages Computations
839‑025‑0054
Exemption from Overtime Pay Requirements on Public Improvement Projects
839‑025‑0060
Apprentices Working upon Public Works Projects
839‑025‑0065
Trainees Working upon Public Works Projects
839‑025‑0080
Liability to Workers
839‑025‑0085
Contract Ineligibility
839‑025‑0090
List of Ineligibles
839‑025‑0095
Removal of Names from List of Ineligibles
839‑025‑0100
Exemptions from ORS 279C.800 to 279C.870
839‑025‑0150
Definitions Related to Installation of Art on Public Works
839‑025‑0155
Payment of Prevailing Rate of Wage for the Installation of Art on Public Works Projects
839‑025‑0200
Fees to Be Paid by Public Agency
839‑025‑0210
Adjustment of Fees Paid by Public Agency
839‑025‑0220
Fees for Contract Without Specific Award Amounts
839‑025‑0230
Fees for Contracts with Other Special Circumstances
839‑025‑0300
Actions that Circumvent Payment of Prevailing Wages Prohibited
839‑025‑0310
Division of Projects
839‑025‑0320
Payment of Prevailing Wage by Persons Other than Contractors or Subcontractors Prohibited
839‑025‑0330
Wage Averaging Prohibited
839‑025‑0340
Circumventions of the Prevailing Wage Rate Law
839‑025‑0500
Definitions Related to Civil Penalties for Violations of Prevailing Wage Rates on Public Works Matters
839‑025‑0510
Violations Separate and Distinct
839‑025‑0520
Criteria to Determine Civil Penalty
839‑025‑0530
Violations for Which a Civil Penalty May Be Assessed
839‑025‑0540
Schedule of Civil Penalties
839‑025‑0700
Prevailing Wage Rate Determination/Amendments to Determination
839‑025‑0750
Residential Prevailing Wage Rate Determinations
Last Updated

Jun. 24, 2021

Rule 839-025-0020’s source at or​.us