ORS 279B.405
Protests and judicial review of solicitations


(1)

As used in this section:

(a)

“Brand name” means a brand name specification as defined in ORS 279B.200 (Definitions for ORS 279B.200 to 279B.240).

(b)

“Legally flawed” means that a solicitation document contains terms or conditions that are contrary to law.

(c)

“Unnecessarily restrictive” means that specifications limit competition arbitrarily, without reasonably promoting the fulfillment of the procurement needs of a contracting agency.

(2)

A prospective bidder, proposer or offeror for a public contract solicited under ORS 279B.055 (Competitive sealed bidding), 279B.060 (Competitive sealed proposals) or 279B.085 (Special procurements) may file a protest with the contracting agency if the prospective bidder, proposer or offeror believes that the procurement process is contrary to law or that a solicitation document is unnecessarily restrictive, is legally flawed or improperly specifies a brand name. If a prospective bidder, proposer or offeror fails to timely file such a protest, the prospective bidder, proposer or offeror may not challenge the contract on grounds under this subsection in any future legal or administrative proceeding.

(3)

The contracting agency, pursuant to rules adopted under ORS 279A.065 (Model rules generally), shall notify prospective bidders, proposers or offerors of the time and manner in which a protest under this section may be filed and considered. Before seeking judicial review, a prospective bidder, proposer or offeror must file a protest with the contracting agency and exhaust all available administrative remedies.

(4)

The contracting agency shall consider the protest if the protest is timely filed and contains the following:

(a)

Sufficient information to identify the solicitation that is the subject of the protest;

(b)

The grounds that demonstrate how the procurement process is contrary to law or how the solicitation document is unnecessarily restrictive, is legally flawed or improperly specifies a brand name;

(c)

Evidence or supporting documentation that supports the grounds on which the protest is based; and

(d)

The relief sought.

(5)

If the protest meets the requirements of subsection (4) of this section, the contracting agency shall consider the protest and issue a decision in writing. Otherwise, the contracting agency shall promptly notify the prospective bidder, proposer or offeror that the protest is untimely or that the protest failed to meet the requirements of subsection (4) of this section and give the reasons for the failure.

(6)

The contracting agency shall issue a decision on the protest in accordance with rules adopted under ORS 279A.065 (Model rules generally) no fewer than three business days before bids, proposals or offers are due, unless a written determination is made by the agency that circumstances exist that justify a shorter time limit.

(7)

A decision of a contracting agency on a protest under this section, including a protest of a special procurement, is subject to judicial review only if the action or writ of review is filed before the opening of bids, proposals or offers.

(8)

Intentionally left blank —Ed.

(a)

A decision of a state contracting agency on a protest under this section is reviewable by the Circuit Court for Marion County or the circuit court for the county in which the principal offices of the state contracting agency are located.

(b)

A decision of a local contracting agency on a protest under this section is reviewable by the circuit court for the county in which the principal offices of the local contracting agency are located.

(9)

If judicial review of a contracting agency’s decision on a protest under this section is sought, the contracting agency may not proceed with contract execution unless the contracting agency determines that there is a compelling governmental interest in proceeding or that the goods and services are urgently needed. If the contracting agency makes such a determination, the contracting agency shall set forth the reasons for the determination in writing and immediately provide them to the prospective bidder, proposer or offeror that filed the protest. Thereafter, after joining the contractor as a party to the litigation and upon motion from the person filing the protest, the court may nonetheless stay the performance of the contract if the court finds that the contracting agency’s determination of the existence of a compelling governmental interest in proceeding with contract execution, or the contracting agency’s determination that the goods or services were urgently needed, was not supported by substantial evidence or constituted a manifest abuse of discretion. In granting a stay, the court may require the person seeking the stay to post a bond in an amount sufficient to protect the contracting agency and the public from costs associated with delay in contract performance.

(10)

In its review, the court shall give due deference to any factual decision made by the contracting agency and may not substitute its judgment for that of the contracting agency, but shall review all questions of law de novo. Thereafter:

(a)

If a contract has not been executed and the court rules in favor of the party that sought judicial review, the court shall remand the procurement process to the contracting agency for a determination of whether and how to continue with the procurement process in light of the court’s decision.

(b)

In addition to the relief provided for in paragraph (a) of this subsection, if a contract has been executed, the court shall include in its order a determination whether the party that signed the contract with the contracting agency is entitled to reimbursement under the conditions of, and calculated in the same manner as provided in, ORS 279C.470 (Compensation for contractor on contract declared void by court). Notwithstanding that ORS 279C.470 (Compensation for contractor on contract declared void by court) otherwise applies only to public improvement contracts, under this paragraph the court shall apply ORS 279C.470 (Compensation for contractor on contract declared void by court) to both public improvement contracts and other public contracts of contracting agencies.

(c)

The court may award costs and attorney fees to the prevailing party. [2003 c.794 §84; 2007 c.764 §11]

Source: Section 279B.405 — Protests and judicial review of solicitations, https://www.­oregonlegislature.­gov/bills_laws/ors/ors279B.­html.

279B.005
Definitions
279B.010
Policy
279B.015
Applicability
279B.020
Maximum hours of labor on public contracts
279B.025
Procurement practices regarding recyclable and reusable goods
279B.030
Demonstration that procurement will cost less than performing service with contracting agency’s own personnel and resources or that performing service is not feasible
279B.033
Contents of cost analysis
279B.036
Determination of feasibility of procurement
279B.040
Prohibition on accepting bid or proposal from contractor that advised or assisted contracting agency to develop specifications or solicitation documents
279B.045
Contractor warranty and covenant concerning tax law compliance
279B.050
Methods of source selection
279B.055
Competitive sealed bidding
279B.060
Competitive sealed proposals
279B.065
Small procurements
279B.070
Intermediate procurements
279B.075
Sole-source procurements
279B.080
Emergency procurements
279B.085
Special procurements
279B.100
Cancellation, rejection, delay of invitations for bids or requests for proposals
279B.110
Responsibility of bidders and proposers
279B.112
Personnel deployment disclosure
279B.115
Qualified products lists
279B.120
Prequalification of prospective bidders and proposers
279B.125
Application for prequalification
279B.130
Debarment of prospective bidders and proposers
279B.135
Notice of intent to award
279B.140
Price agreements
279B.145
Finality of determinations
279B.200
Definitions for ORS 279B.200 to 279B.240
279B.205
Specifications to encourage reasonable competition
279B.210
Policy
279B.215
Brand name or equal specification
279B.220
Conditions concerning payment, contributions, liens, withholding
279B.225
Condition concerning salvaging, recycling, composting or mulching yard waste material
279B.230
Condition concerning payment for medical care and providing workers’ compensation
279B.235
Condition concerning hours of labor
279B.240
Exclusion of recycled oils prohibited
279B.270
State contracting agencies to use recovered resources and recycled materials
279B.275
Purchase of goods containing recycled polyethylene material
279B.280
Use of recycled products when economically feasible
279B.283
Condition concerning use of conflict minerals
279B.400
Protests and judicial review of approvals of special procurements
279B.405
Protests and judicial review of solicitations
279B.410
Protests of contract award
279B.415
Judicial review of protests of contract award
279B.420
Judicial review of other violations
279B.425
Review of prequalification and debarment decisions