ORS 279B.415
Judicial review of protests of contract award


(1)

As used in this section, “bidder” includes a person who submits a proposal to a public contracting agency pursuant to a request for proposals.

(2)

A decision by a state contracting agency on a protest of a contract award is reviewable by the Circuit Court for Marion County or the circuit court for the county in which the principal offices of the state contracting agency are located. A decision by a local contracting agency on a protest of a contract award is reviewable by the circuit court for the county in which the principal offices of the local contracting agency are located.

(3)

To obtain review, a complainant must commence an action before the contract that is the subject of the protest is approved by the Attorney General, if required by ORS 291.047 (Public contract approval by Attorney General), and executed by the contracting agency. In the complaint, the complainant shall state the nature of the complainant’s interest, the facts showing how the complainant is adversely affected or aggrieved by the contracting agency’s decision and the basis upon which the decision should be reversed or remanded. The complainant shall join as parties all bidders that would be in line for an award of the contract ahead of the complainant. If injunctive relief is sought, the court may require the person seeking a stay to post a bond in an amount sufficient to protect the contracting agency and the public from costs associated with delay in execution of the contract.

(4)

When judicial review is sought, the contracting agency may not proceed with contract execution unless the contracting agency determines that there is a compelling governmental interest in proceeding or that the goods and services are urgently needed. If the contracting agency makes such a determination, the contracting agency shall set forth the reasons for the determination in writing and immediately provide them to the complainant. Thereafter, upon motion from the complainant, the court may nonetheless stay the performance of the contract if the court finds that the contracting agency’s determination of the existence of a compelling governmental interest in proceeding with contract execution, or the contracting agency’s determination that the goods or services were urgently needed, was not supported by substantial evidence or constituted a manifest abuse of discretion. In granting a stay, the court may require the person seeking the stay to post a bond in an amount sufficient to protect the contracting agency and the public from costs associated with delay in contract performance.

(5)

The court shall review the matter without a jury and shall consider only those grounds the complainant raised in the protest to the contracting agency.

(6)

The court shall remand the matter to the contracting agency for a further decision if:

(a)

Substantial evidence does not exist to support the contracting agency’s decision. Substantial evidence exists to support a finding of fact when the record, viewed as a whole, would permit a reasonable person to make that finding;

(b)

The contracting agency’s decision was outside the range of discretion delegated to the contracting agency by law;

(c)

The decision was inconsistent with a contracting agency rule, an officially stated contracting agency position or an officially stated prior contracting agency practice, if the inconsistency is not explained by the contracting agency; or

(d)

The decision was in violation of a constitutional or statutory provision.

(7)

Intentionally left blank —Ed.

(a)

In addition to remanding the decision to the contracting agency, the court may order such ancillary relief, such as the cost of bid preparation, as the court finds necessary to redress the effects of official action wrongfully taken or withheld. Ancillary relief does not include the award of a contract to the complainant or the award of lost profits or other damages.

(b)

If a contract has not been executed and the court rules in favor of the complainant, the court shall remand the matter to the contracting agency for a determination whether to continue with the procurement process in light of the court’s decision.

(c)

If a contract has been executed, in addition to the relief provided for in paragraph (a) of this subsection, the court shall include in its order a determination whether the party that signed the contract with the contracting agency is entitled to reimbursement under the conditions of, and calculated in the same manner as provided in, ORS 279C.470 (Compensation for contractor on contract declared void by court). Notwithstanding that ORS 279C.470 (Compensation for contractor on contract declared void by court) otherwise applies only to public improvement contracts, under this paragraph the court shall apply ORS 279C.470 (Compensation for contractor on contract declared void by court) to both public improvement contracts and other public contracts of contracting agencies.

(d)

The court may award costs and attorney fees to the prevailing party. [2003 c.794 §86; 2007 c.764 §12]

Source: Section 279B.415 — Judicial review of protests of contract award, https://www.­oregonlegislature.­gov/bills_laws/ors/ors279B.­html.

279B.005
Definitions
279B.010
Policy
279B.015
Applicability
279B.020
Maximum hours of labor on public contracts
279B.025
Procurement practices regarding recyclable and reusable goods
279B.030
Demonstration that procurement will cost less than performing service with contracting agency’s own personnel and resources or that performing service is not feasible
279B.033
Contents of cost analysis
279B.036
Determination of feasibility of procurement
279B.040
Prohibition on accepting bid or proposal from contractor that advised or assisted contracting agency to develop specifications or solicitation documents
279B.045
Contractor warranty and covenant concerning tax law compliance
279B.050
Methods of source selection
279B.055
Competitive sealed bidding
279B.060
Competitive sealed proposals
279B.065
Small procurements
279B.070
Intermediate procurements
279B.075
Sole-source procurements
279B.080
Emergency procurements
279B.085
Special procurements
279B.100
Cancellation, rejection, delay of invitations for bids or requests for proposals
279B.110
Responsibility of bidders and proposers
279B.112
Personnel deployment disclosure
279B.115
Qualified products lists
279B.120
Prequalification of prospective bidders and proposers
279B.125
Application for prequalification
279B.130
Debarment of prospective bidders and proposers
279B.135
Notice of intent to award
279B.140
Price agreements
279B.145
Finality of determinations
279B.200
Definitions for ORS 279B.200 to 279B.240
279B.205
Specifications to encourage reasonable competition
279B.210
Policy
279B.215
Brand name or equal specification
279B.220
Conditions concerning payment, contributions, liens, withholding
279B.225
Condition concerning salvaging, recycling, composting or mulching yard waste material
279B.230
Condition concerning payment for medical care and providing workers’ compensation
279B.235
Condition concerning hours of labor
279B.240
Exclusion of recycled oils prohibited
279B.270
State contracting agencies to use recovered resources and recycled materials
279B.275
Purchase of goods containing recycled polyethylene material
279B.280
Use of recycled products when economically feasible
279B.283
Condition concerning use of conflict minerals
279B.400
Protests and judicial review of approvals of special procurements
279B.405
Protests and judicial review of solicitations
279B.410
Protests of contract award
279B.415