OAR 137-049-0260
Request for Clarification or Change; Solicitation Protests


(1)

Clarification. Prior to the deadline for submitting a Written request for change or protest, an Offeror may request that the Contracting Agency clarify any provision of the Solicitation Document. The Contracting Agency’s clarification to an Offeror, whether orally or in Writing, does not change the Solicitation Document and is not binding on the Contracting Agency unless the Contracting Agency amends the Solicitation Document by Addendum.

(2)

Request for Change.

(a)

Delivery. An Offeror may request in Writing a change to the Specifications or Contract terms and conditions. Unless otherwise specified in the Solicitation Document, an Offeror must deliver the Written request for change to the Contracting Agency not less than 10 Days prior to Closing;

(b)

Content of Request for Change.

(A)

An Offeror’s Written request for change shall include a statement of the requested change(s) to the Contract terms and conditions, including any Specifications, together with the reason for the requested change.

(B)

An Offeror shall mark its request for change as follows:
(i)
“Contract Provision Request for Change”; and
(ii)
Solicitation Document number (or other identification as specified in the Solicitation Document).

(3)

Protest.

(a)

Delivery. An Offeror may protest Specifications or Contract terms and conditions. Unless otherwise specified in the Solicitation Document, an Offeror must deliver a Written protest on those matters to the Contracting Agency not less than 10 Days prior to Closing;

(b)

Content of Protest.

(A)

An Offeror’s Written protest shall include:
(i)
A detailed statement of the legal and factual grounds for the protest;
(ii)
A description of the resulting prejudice to the Offeror; and
(iii)
A statement of the desired changes to the Contract terms and conditions, including any Specifications.

(B)

An Offeror shall mark its protest as follows:
(i)
“Contract Provision Protest”; and
(ii)
Solicitation Document number (or other identification as specified in the Solicitation Document).

(4)

Contracting Agency Response. The Contracting Agency is not required to consider an Offeror’s request for change or protest after the deadline established for submitting such request or protest. The Contracting Agency shall provide notice to the applicable Person if it entirely rejects a protest. If the Contracting Agency agrees with the Person’s request or protest, in whole or in part, the Contracting Agency shall either issue an Addendum reflecting its determination under OAR 137-049-0260 (Request for Clarification or Change; Solicitation Protests) or cancel the solicitation under OAR 137-049-0270 (Cancellation of Solicitation Document).

(5)

Extension of Closing. If a Contracting Agency receives a Written request for change or protest from an Offeror in accordance with this rule, the Contracting Agency may extend Closing if the Contracting Agency determines an extension is necessary to consider the request or protest and issue an Addendum, if any, to the Solicitation Document.

Source: Rule 137-049-0260 — Request for Clarification or Change; Solicitation Protests, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=137-049-0260.

137‑049‑0100
Application
137‑049‑0110
Policies
137‑049‑0120
Definitions
137‑049‑0130
Competitive Bidding Requirement
137‑049‑0140
Contracts for Construction Other Than Public Improvements
137‑049‑0150
Emergency Contracts
137‑049‑0160
Intermediate Procurements
137‑049‑0200
Solicitation Documents
137‑049‑0210
Notice and Advertising Requirements
137‑049‑0220
Prequalification of Offerors
137‑049‑0230
Eligibility to Bid or Propose
137‑049‑0240
Pre-Offer Conferences
137‑049‑0250
Addenda to Solicitation Documents
137‑049‑0260
Request for Clarification or Change
137‑049‑0270
Cancellation of Solicitation Document
137‑049‑0280
Offer Submissions
137‑049‑0290
Bid or Proposal Security
137‑049‑0300
Facsimile Bids and Proposals
137‑049‑0310
Electronic Procurement
137‑049‑0320
Pre-Closing Modification or Withdrawal of Offers
137‑049‑0330
Receipt, Opening and Recording of Offers
137‑049‑0340
Late Bids, Late Withdrawals and Late Modifications
137‑049‑0350
Mistakes
137‑049‑0360
First-Tier Subcontractors
137‑049‑0370
Disqualification of Persons
137‑049‑0380
Bid or Proposal Evaluation Criteria
137‑049‑0390
Offer Evaluation and Award
137‑049‑0395
Notice of Intent to Award
137‑049‑0400
Documentation of Award
137‑049‑0410
Time for Contracting Agency Acceptance
137‑049‑0420
Negotiation With Bidders Prohibited
137‑049‑0430
Negotiation When Bids Exceed Cost Estimate
137‑049‑0440
Rejection of Offers
137‑049‑0450
Protest of Contractor Selection, Contract Award
137‑049‑0460
Performance and Payment Security
137‑049‑0470
Substitute Contractor
137‑049‑0490
Foreign Contractor
137‑049‑0600
Purpose
137‑049‑0610
Definitions for Alternative Contracting Methods
137‑049‑0620
Use of Alternative Contracting Methods
137‑049‑0630
Findings, Notice and Hearing
137‑049‑0640
Competitive Proposals
137‑049‑0645
Requests for Qualifications (RFQ)
137‑049‑0650
Requests for Proposals (“RFP”)
137‑049‑0660
RFP Pricing Mechanisms
137‑049‑0670
Design-Build Contracts
137‑049‑0680
Energy Savings Performance Contracts (ESPC)
137‑049‑0690
Construction Manager/General Contractor Services (“CM/GC Services”)
137‑049‑0800
Required Contract Clauses
137‑049‑0810
Waiver of Delay Damages Against Public Policy
137‑049‑0815
BOLI Public Works Bond
137‑049‑0820
Retainage
137‑049‑0830
Contractor Progress Payments
137‑049‑0840
Interest
137‑049‑0850
Final Inspection
137‑049‑0860
Public Works Contracts
137‑049‑0870
Specifications
137‑049‑0880
Records Maintenance
137‑049‑0890
Contracting Agency Payment for Unpaid Labor or Supplies
137‑049‑0900
Contract Suspension
137‑049‑0910
Changes to the Work and Contract Amendments
Last Updated

Jun. 8, 2021

Rule 137-049-0260’s source at or​.us