OAR 137-049-0630
Findings, Notice and Hearing


(1)

Cost Savings and Other Substantial Benefits Factors. When Findings are required under ORS 279C.335 (Competitive bidding) to exempt a Contract or class of Contracts from the competitive bidding requirements, the “substantial cost savings and other substantial benefits” criteria at 279C.335 (Competitive bidding)(2)(b) require consideration of the type, cost and amount of the Contract and, to the extent applicable, the other factors set forth in 279C.335 (Competitive bidding)(2)(b). If a particular factor has no application whatsoever to the particular Public Improvement Contract or class of Public Improvement Contracts, the Director of the Oregon Department of Administrative Services, the Director of Transportation or the local contract review board does not need to consider that factor, and the Contracting Agency is not required to address the factor, other than to explain why the factor has no application whatsoever to the particular Public Improvement Contract or class of Public Improvement Contracts..

(2)

Required Information. The statutory definition of “Findings” at ORS 279C.330 (“Findings” defined)(2), which applies to exemptions from competitive bidding under ORS 279C.335 (Competitive bidding), means the justification for a Contracting Agency or State Agency conclusion regarding the factors listed in both ORS 279C.335 (Competitive bidding)(2)(a) and 279C.335 (Competitive bidding)(2)(b) or, in the alternative, both 279C.335 (Competitive bidding)(2)(a) and 279C.335 (Competitive bidding)(2)(c). For an exemption granted by the Director of the Oregon Department of Administrative Services or the Director of Transportation under ORS 279C.350 (Exemption procedure) by order, however, the order must also include the findings listed in ORS 279C.330 (“Findings” defined)(1).

(3)

Addressing Cost Savings. Accordingly, when the Contract or class of Contracts under consideration for an exemption contemplates the use of Alternative Contracting Methods, the “substantial cost savings and other substantial benefits” requirement may be addressed by a combination of:

(a)

Specified Findings that address the factors and other information specifically identified by statute, including, but not limited to, an analysis or reasonable forecast of present and future cost savings and other substantial benefits; and

(b)

Additional Findings that address industry practices, surveys, trends, past experiences, evaluations of completed projects required by ORS 279C.355 (Evaluation of public improvement projects not contracted by competitive bidding) and related information regarding the expected benefits and drawbacks of particular Alternative Contracting Methods. To the extent practicable, such Findings shall relate back to the specific characteristics of the project or projects at issue in the exemption request.

(c)

As an alternative to the “substantial cost savings and other substantial benefits” requirement in ORS 279C.335 (Competitive bidding)(2)(b), if an Alternative Contracting Method has not been previously used, the Contracting Agency or State Agency may make a Finding that identifies the project as a “pilot project” under ORS 279C.335 (Competitive bidding)(2)(c). Nevertheless, the Contracting Agency or State Agency must still make the findings required in ORS 279C.335 (Competitive bidding)(2)(a).

(4)

Favoritism and Competition. The criteria at ORS 279C.335 (Competitive bidding)(2)(a) that the exemption “is unlikely to encourage favoritism” or “substantially diminish competition” may be addressed in contemplating the use of Alternative Contracting Methods by specifying the manner in which an RFP process will be utilized, that the Procurement will be formally advertised with public notice and disclosure of the planned Alternative Contracting Method, competition will be encouraged, Award made based upon identified selection criteria and an opportunity to protest that Award.

(5)

Descriptions. Findings supporting a competitive bidding exemption must describe with specificity any Alternative Contracting Method to be used in lieu of competitive bidding, including, but not limited to, whether a one-step (request for Proposals), two-step (beginning with a Request for Qualifications, followed by a request for Proposals) or other solicitation process will be utilized. The Findings may also describe anticipated characteristics or features of the resulting Public Improvement Contract. However, the purpose of an exemption from competitive bidding is limited to a determination of the Procurement method. Any unnecessary or incidental descriptions of the specific details of the anticipated Contract within the supporting Findings are not binding upon the Contracting Agency. The parameters of the Public Improvement Contract are those characteristics or specifics that are announced in the Solicitation Document.

(6)

Class Exemptions. In making the findings supporting a class exemption the Contracting Agency shall clearly identify the “class” with respect to its defining characteristics, pursuant to the requirements of ORS 279C.335 (Competitive bidding)(3). The class must meet the following requirements:

(a)

The class cannot be based on a single characteristic or factor, so that an Agency directly or indirectly creates a class whereby the Agency uses, for example, the CM/GC Method for all Agency construction projects or all Agency construction projects over a particular dollar amount, unidentified future Agency construction projects of a particular work category, or all Agency construction projects from a particular funding source such as the sale of bonds; and

(b)

The class must include a combination of factors, be defined by the Agency through characteristics that reasonably relate to the exemption criteria set forth in ORS 279C.335 (Competitive bidding)(2) and must reflect a detailed evaluation of those characteristics so that the class is defined in a limited way that effectively meets the Agency’s objectives while allowing for impartial and open competition, and protecting the integrity of the exemption process. An example of a class that might be permitted under the statute is a series of projects, such as a specific group of building renovation projects, that

(A)

Involve renovations for a common purpose;

(B)

Require completion on a related schedule in order to avoid unnecessary disruption of Contracting Agency operations;

(C)

Share common characteristics, such as historic building considerations, the presence of asbestos or other hazardous substances, or the presence of agency staff during construction;

(D)

Otherwise possess characteristics that meet the requirements of ORS 279C.335 (Competitive bidding)(2); and

(E)

Otherwise meet the requirements of the Director of the Oregon Department of Administrative Services, the Director of Transportation or the local contract review board, as applicable.

(7)

Public Hearing. Before final adoption of Findings exempting a Public Improvement Contract or class of Contracts from the requirement of competitive bidding, a Contracting Agency or State Agency shall give notice and hold a public hearing as required by ORS 279C.335 (Competitive bidding)(5). The hearing shall be for the purpose of receiving public comment on the Contracting Agency’s or State Agency’s draft Findings.

(8)

Prior Review of Draft Findings. State Contracting Agencies shall submit draft Findings to their Contract Review Authority for review and concurrence prior to advertising the public hearing required by ORS 279C.335 (Competitive bidding)(5). State Contracting Agencies shall also submit draft Findings to the Department of Justice for review and comment prior to advertising the public hearing.

Source: Rule 137-049-0630 — Findings, Notice and Hearing, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=137-049-0630.

137‑049‑0100
Application
137‑049‑0110
Policies
137‑049‑0120
Definitions
137‑049‑0130
Competitive Bidding Requirement
137‑049‑0140
Contracts for Construction Other Than Public Improvements
137‑049‑0150
Emergency Contracts
137‑049‑0160
Intermediate Procurements
137‑049‑0200
Solicitation Documents
137‑049‑0210
Notice and Advertising Requirements
137‑049‑0220
Prequalification of Offerors
137‑049‑0230
Eligibility to Bid or Propose
137‑049‑0240
Pre-Offer Conferences
137‑049‑0250
Addenda to Solicitation Documents
137‑049‑0260
Request for Clarification or Change
137‑049‑0270
Cancellation of Solicitation Document
137‑049‑0280
Offer Submissions
137‑049‑0290
Bid or Proposal Security
137‑049‑0300
Facsimile Bids and Proposals
137‑049‑0310
Electronic Procurement
137‑049‑0320
Pre-Closing Modification or Withdrawal of Offers
137‑049‑0330
Receipt, Opening and Recording of Offers
137‑049‑0340
Late Bids, Late Withdrawals and Late Modifications
137‑049‑0350
Mistakes
137‑049‑0360
First-Tier Subcontractors
137‑049‑0370
Disqualification of Persons
137‑049‑0380
Bid or Proposal Evaluation Criteria
137‑049‑0390
Offer Evaluation and Award
137‑049‑0395
Notice of Intent to Award
137‑049‑0400
Documentation of Award
137‑049‑0410
Time for Contracting Agency Acceptance
137‑049‑0420
Negotiation With Bidders Prohibited
137‑049‑0430
Negotiation When Bids Exceed Cost Estimate
137‑049‑0440
Rejection of Offers
137‑049‑0450
Protest of Contractor Selection, Contract Award
137‑049‑0460
Performance and Payment Security
137‑049‑0470
Substitute Contractor
137‑049‑0490
Foreign Contractor
137‑049‑0600
Purpose
137‑049‑0610
Definitions for Alternative Contracting Methods
137‑049‑0620
Use of Alternative Contracting Methods
137‑049‑0630
Findings, Notice and Hearing
137‑049‑0640
Competitive Proposals
137‑049‑0645
Requests for Qualifications (RFQ)
137‑049‑0650
Requests for Proposals (“RFP”)
137‑049‑0660
RFP Pricing Mechanisms
137‑049‑0670
Design-Build Contracts
137‑049‑0680
Energy Savings Performance Contracts (ESPC)
137‑049‑0690
Construction Manager/General Contractor Services (“CM/GC Services”)
137‑049‑0800
Required Contract Clauses
137‑049‑0810
Waiver of Delay Damages Against Public Policy
137‑049‑0815
BOLI Public Works Bond
137‑049‑0820
Retainage
137‑049‑0830
Contractor Progress Payments
137‑049‑0840
Interest
137‑049‑0850
Final Inspection
137‑049‑0860
Public Works Contracts
137‑049‑0870
Specifications
137‑049‑0880
Records Maintenance
137‑049‑0890
Contracting Agency Payment for Unpaid Labor or Supplies
137‑049‑0900
Contract Suspension
137‑049‑0910
Changes to the Work and Contract Amendments
Last Updated

Jun. 24, 2021

Rule 137-049-0630’s source at or​.us