OAR 137-049-0300
Facsimile Bids and Proposals


(1)

Contracting Agency Authorization. A Contracting Agency may authorize Offerors to submit facsimile Offers. If the Contracting Agency determines that Bid or Proposal security is or will be required, the Contracting Agency shall not authorize facsimile Offers unless the Contracting Agency has established a method for receipt of such security. Prior to authorizing the submission of facsimile Offers, the Contracting Agency shall determine that the Contracting Agency’s equipment and personnel are capable of receiving the size and volume of anticipated Offers within a short period of time. In addition, the Contracting Agency shall establish administrative procedures and controls:

(a)

To receive, identify, record and safeguard facsimile Offers;

(b)

To ensure timely delivery of Offers to the location of Opening; and

(c)

To preserve the Offers as sealed.

(2)

Provisions To Be Included in Solicitation Document. In addition to all other requirements, if the Contracting Agency authorizes a facsimile Offer for Bids or Proposals, the Contracting Agency shall include in the Solicitation Document (other than in a Request for Quotes) the following:

(a)

A provision substantially in the form of the following: “A ‘facsimile Offer,’ as used in this Solicitation Document, means an Offer, modification of an Offer, or withdrawal of an Offer that is transmitted to and received by the Contracting Agency via a facsimile machine”;

(b)

A provision substantially in the form of the following: “Offerors may submit facsimile Offers in response to this Solicitation Document. The entire response must arrive at the place and by the time specified in this Solicitation Document.”;

(c)

A provision that requires Offerors to Sign their facsimile Offers;

(d)

A provision substantially in the form of the following: “The Contracting Agency reserves the right to Award the Contract solely on the basis of the facsimile Offer. However, upon the Contracting Agency’s request the apparent successful Offeror shall promptly submit its complete original Signed Offer.”;

(e)

The data and compatibility characteristics of the Contracting Agency’s receiving facsimile machine as follows:

(A)

Telephone number; and

(B)

Compatibility characteristics, e.g., make and model number, receiving speed, communications protocol; and

(f)

A provision that the Contracting Agency is not responsible for any failure attributable to the transmission or receipt of the facsimile Offer including, but not limited to the following:

(A)

Receipt of garbled or incomplete documents;

(B)

Availability or condition of the receiving facsimile machine;

(C)

Incompatibility between the sending and receiving facsimile machine;

(D)

Delay in transmission or receipt of documents;

(E)

Failure of the Offeror to properly identify the Offer documents;

(F)

Illegibility of Offer documents; and

(G)

Security and confidentiality of data.

Source: Rule 137-049-0300 — Facsimile Bids and Proposals, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=137-049-0300.

137‑049‑0100
Application
137‑049‑0110
Policies
137‑049‑0120
Definitions
137‑049‑0130
Competitive Bidding Requirement
137‑049‑0140
Contracts for Construction Other Than Public Improvements
137‑049‑0150
Emergency Contracts
137‑049‑0160
Intermediate Procurements
137‑049‑0200
Solicitation Documents
137‑049‑0210
Notice and Advertising Requirements
137‑049‑0220
Prequalification of Offerors
137‑049‑0230
Eligibility to Bid or Propose
137‑049‑0240
Pre-Offer Conferences
137‑049‑0250
Addenda to Solicitation Documents
137‑049‑0260
Request for Clarification or Change
137‑049‑0270
Cancellation of Solicitation Document
137‑049‑0280
Offer Submissions
137‑049‑0290
Bid or Proposal Security
137‑049‑0300
Facsimile Bids and Proposals
137‑049‑0310
Electronic Procurement
137‑049‑0320
Pre-Closing Modification or Withdrawal of Offers
137‑049‑0330
Receipt, Opening and Recording of Offers
137‑049‑0340
Late Bids, Late Withdrawals and Late Modifications
137‑049‑0350
Mistakes
137‑049‑0360
First-Tier Subcontractors
137‑049‑0370
Disqualification of Persons
137‑049‑0380
Bid or Proposal Evaluation Criteria
137‑049‑0390
Offer Evaluation and Award
137‑049‑0395
Notice of Intent to Award
137‑049‑0400
Documentation of Award
137‑049‑0410
Time for Contracting Agency Acceptance
137‑049‑0420
Negotiation With Bidders Prohibited
137‑049‑0430
Negotiation When Bids Exceed Cost Estimate
137‑049‑0440
Rejection of Offers
137‑049‑0450
Protest of Contractor Selection, Contract Award
137‑049‑0460
Performance and Payment Security
137‑049‑0470
Substitute Contractor
137‑049‑0490
Foreign Contractor
137‑049‑0600
Purpose
137‑049‑0610
Definitions for Alternative Contracting Methods
137‑049‑0620
Use of Alternative Contracting Methods
137‑049‑0630
Findings, Notice and Hearing
137‑049‑0640
Competitive Proposals
137‑049‑0645
Requests for Qualifications (RFQ)
137‑049‑0650
Requests for Proposals (“RFP”)
137‑049‑0660
RFP Pricing Mechanisms
137‑049‑0670
Design-Build Contracts
137‑049‑0680
Energy Savings Performance Contracts (ESPC)
137‑049‑0690
Construction Manager/General Contractor Services (“CM/GC Services”)
137‑049‑0800
Required Contract Clauses
137‑049‑0810
Waiver of Delay Damages Against Public Policy
137‑049‑0815
BOLI Public Works Bond
137‑049‑0820
Retainage
137‑049‑0830
Contractor Progress Payments
137‑049‑0840
Interest
137‑049‑0850
Final Inspection
137‑049‑0860
Public Works Contracts
137‑049‑0870
Specifications
137‑049‑0880
Records Maintenance
137‑049‑0890
Contracting Agency Payment for Unpaid Labor or Supplies
137‑049‑0900
Contract Suspension
137‑049‑0910
Changes to the Work and Contract Amendments
Last Updated

Jun. 8, 2021

Rule 137-049-0300’s source at or​.us