OAR 137-049-0680
Energy Savings Performance Contracts (ESPC)


(1)

Generally. These OAR 137-049-0600 (Purpose) to 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”)) rules include a limited, efficient method for Contracting Agencies to enter into ESPCs outside the competitive bidding requirements of ORS 279C.335 (Competitive bidding) for existing buildings or structures, but not for new construction. See ORS 279C.335 (Competitive bidding)(1)(f). If a Contracting Agency chooses not to utilize the ESPC Procurement method provided for by these OAR 137-049-0600 (Purpose) to 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”)) rules, the Contracting Agency may still enter into an ESPC by complying with the competitive bidding exemption process set forth in ORS 279C.335 (Competitive bidding), or by otherwise complying with the Procurement requirements applicable to any Contracting Agency not subject to all the requirements of 279C.335 (Competitive bidding).

(2)

ESPC Contracting Method. The ESPC form of contracting, as defined at OAR 137-049-0610 (Definitions for Alternative Contracting Methods)(6), has unique technical complexities associated with the determination of what ECMs are feasible for the Contracting Agency, as well as the additional technical complexities associated with a Design-Build Contract. Contracting Agencies shall only utilize the ESPC contracting method with the assistance of knowledgeable staff or consultants who are experienced in its use. In order to utilize the ESPC contracting process, the Contracting Agency must be able to reasonably anticipate one or more of the following types of benefits:

(a)

Obtaining, through an ESCO, the following types of integrated Personal Services and Work: facility profiling, energy baseline studies, ECMs, Technical Energy Audits, project development planning, engineering design, plan preparation, cost estimating, life cycle costing, construction administration, project management, construction, quality control, operations and maintenance staff training, commissioning services, M & V services and required documentation as a fully integrated function with a single point of responsibility;

(b)

Obtaining, through an ESCO, an Energy Savings Guarantee;

(c)

Integrating the Technical Energy Audit phase and the Project Development Plan phase into the design and construction phase of Work on the project;

(d)

Reducing the risk of design flaws, misunderstandings and conflicts inherent in the construction process, through the integration of ESPC Personal Services and Work;

(e)

Obtaining innovative design solutions through the collaboration of the members of the ESCO integrated ESPC team;

(f)

Integrating cost-effective ECMs into an existing building or structure, so that the ECMs pay for themselves through savings realized over the useful life of the ECMs;

(g)

Preliminary design, development, implementation and an Energy Savings Guarantee of ECMs into an existing building or structure through an ESPC, as a distinct part of a major remodel of that building or structure that is being performed under a separate remodeling Contract; and

(h)

Satisfying local energy efficiency design criteria or requirements.

(3)

Authority. Contracting Agencies desiring to pursue an exemption from the competitive bidding requirements of ORS 279C.335 (Competitive bidding) (and, if applicable, ORS 351.086), shall utilize the ESPC form of contracting only in accordance with the requirements of these OAR 137-049-0600 (Purpose) to 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”)) rules.

(4)

No Findings Required. A Contracting Agency is only required to comply with the ESPC contracting procedures set forth in these OAR 137-049-0600 (Purpose) to 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”)) rules in order for the ESPC to be exempt from the competitive bidding processes of ORS 279C.335 (Competitive bidding). No Findings are required for an ESPC to be exempt from the competitive bidding process for Public Improvement Contracts pursuant to 279C.335 (Competitive bidding), unless the Contracting Agency is subject to the requirements of 279C.335 (Competitive bidding) and chooses not to comply with the ESPC contracting procedures set forth in OAR 137-049-0600 (Purpose) to 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”)).

(5)

Selection. ESPC selection criteria may include those factors set forth above in OAR 137-049-0640 (Competitive Proposals; Procedure)(2)(a), (b), (c) and (d). Since the Energy Savings Guarantee is such a fundamental component in the ESPC contracting process, Proposers must disclose in their Proposals the identity of any Person providing (directly or indirectly) any Energy Savings Guarantee that may be offered by the successful ESCO during the course of the performance of the ESPC, along with any financial statements and related information pertaining to any such Person.

(6)

QBS Inapplicable. Because the value of construction Work predominates in the ESPC method of contracting, the qualifications based selection (QBS) process mandated by ORS 279C.110 (Selection procedures for consultants to provide services) for State Contracting Agencies in obtaining certain consultant services is not applicable.

(7)

Licensing. If the ESCO is not an Oregon licensed design professional, the Contracting Agency shall require that the ESCO disclose in the ESPC that it is not an Oregon licensed design professional, and identify the Oregon licensed design professional(s) who will provide design services. See ORS 671.030 (Activities not considered as “practice of architecture”)(5) regarding the offer of architectural services, and 672.060 (Activities not requiring registration)(11) regarding the offer of engineering services that are appurtenant to construction Work.

(8)

Performance Security. At the point in the ESPC when the parties enter into a binding Contract that constitutes a Design-Build Contract, the ESCO must provide a performance bond and a payment bond, each for 100% of the full Contract Price, including the construction Work and design and related Personal Services specified in the ESPC Design-Build Contract, pursuant to ORS 279C.380 (Performance bond)(1)(a). For ESPC Design-Build Contracts, these “design and related services” include conventional design services, commissioning services, training services for the Contracting Agency’s operations and maintenance staff, and any similar Personal Services provided by the ESCO under the ESPC Design-Build Contract prior to final completion of construction. M & V services, and any Personal Services or Work associated with the ESCO’s Energy Savings Guarantee are not included in these 279C.380 (Performance bond)(1)(a) “design and related services.” Nevertheless, a Contracting Agency may require that the ESCO provide performance security for M & V services and any Personal Services or Work associated with the ESCO’s Energy Savings Guarantee, if the Contracting Agency so provides in the RFP.

(9)

Contracting Requirements. Contracting Agencies shall conform their ESPC contracting practices to the following requirements:

(a)

General ESPC Contracting Practices. An ESPC involves a multi-phase project, which includes the following contractual elements:

(A)

A contractual structure which includes general Contract terms describing the relationship of the parties, the various phases of the Work, the contractual terms governing the Technical Energy Audit for the project, the contractual terms governing the Project Development Plan for the project, the contractual terms governing the final design and construction of the project, the contractual terms governing the performance of the M & V services for the project, and the detailed provisions of the ESCO’s Energy Savings Guarantee for the project.

(B)

The various phases of the ESCO’s Work will include the following:
(i)
The Technical Energy Audit phase of the Work;
(ii)
The Project Development Plan phase of the Work;
(iii)
A third phase of the Work that constitutes a Design-Build Contract, during which the ESCO completes any plans and Specifications required to implement the ECMs that have been agreed to by the parties to the ESPC, and the ESCO performs all construction, commissioning, construction administration and related Personal Services or Work to actually construct the project; and
(iv)
A final phase of the Work, whereby the ESCO, independently or in cooperation with an independent consultant hired by the Contracting Agency, performs M & V services to ensure that the Energy Savings Guarantee identified by the ESCO in the earlier phases of the Work and agreed to by the parties has actually been achieved.

(b)

Design-Build Contracting Requirements in ESPCs. At the point in the ESPC when the parties enter into a binding Contract that constitutes a Design-Build Contract, the Contracting Agency shall conform its Design-Build contracting practices to the Design-Build contracting requirements set forth in OAR 137-040-0560(7) above.

(c)

Pricing Alternatives. The Contracting Agency may utilize one of the following pricing alternatives in an ESPC:

(A)

A fixed price for each phase of the Personal Services and Work to be provided by the ESCO;

(B)

A cost reimbursement pricing mechanism, with a maximum not-to-exceed price or a GMP; or

(C)

A combination of a fixed fee for certain components of the Personal Services to be performed, a cost reimbursement pricing mechanism for the construction Work to be performed with a GMP, a single or annual fixed fee for M & V services to be performed for an identified time period after final completion of the construction Work, and a single or annual Energy Savings Guarantee fixed fee payable for an identified time period after final completion of the construction Work that is conditioned on certain energy savings being achieved at the facility by the ECMs that have been implemented by the ESCO during the project (in the event an annual M & V services fee and annual Energy Savings Guarantee fee is utilized by the parties, the parties may provide in the Design-Build Contract that, at the sole option of the Contracting Agency, the ESCO’s M & V services may be terminated prior to the completion of the M & V/Energy Savings Guarantee period and the Contracting Agency’s future obligation to pay the M & V services fee and Energy Savings Guarantee fee will likewise be terminated, under terms agreed to by the parties).

(d)

Permitted ESPC Scope of Work. The scope of Work under the ESPC is restricted to implementation and installation of ECMs, as well as other Work on building systems or building components that are directly related to the ECMs, and that, as an integrated unit, will pay for themselves over the useful life of the ECMs installed. The permitted scope of Work for ESPCs resulting from a solicitation under these 137-049-0600 (Purpose) to 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”)) rules does not include maintenance services for the project facility.

Source: Rule 137-049-0680 — Energy Savings Performance Contracts (ESPC), https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=137-049-0680.

137–049–0100
Application
137–049–0110
Policies
137–049–0120
Definitions
137–049–0130
Competitive Bidding Requirement
137–049–0140
Contracts for Construction Other Than Public Improvements
137–049–0150
Emergency Contracts
137–049–0160
Intermediate Procurements
137–049–0200
Solicitation Documents
137–049–0210
Notice and Advertising Requirements
137–049–0220
Prequalification of Offerors
137–049–0230
Eligibility to Bid or Propose
137–049–0240
Pre-Offer Conferences
137–049–0250
Addenda to Solicitation Documents
137–049–0260
Request for Clarification or Change
137–049–0270
Cancellation of Solicitation Document
137–049–0280
Offer Submissions
137–049–0290
Bid or Proposal Security
137–049–0300
Facsimile Bids and Proposals
137–049–0310
Electronic Procurement
137–049–0320
Pre-Closing Modification or Withdrawal of Offers
137–049–0330
Receipt, Opening and Recording of Offers
137–049–0340
Late Bids, Late Withdrawals and Late Modifications
137–049–0350
Mistakes
137–049–0360
First-Tier Subcontractors
137–049–0370
Disqualification of Persons
137–049–0380
Bid or Proposal Evaluation Criteria
137–049–0390
Offer Evaluation and Award
137–049–0395
Notice of Intent to Award
137–049–0400
Documentation of Award
137–049–0410
Time for Contracting Agency Acceptance
137–049–0420
Negotiation With Bidders Prohibited
137–049–0430
Negotiation When Bids Exceed Cost Estimate
137–049–0440
Rejection of Offers
137–049–0450
Protest of Contractor Selection, Contract Award
137–049–0460
Performance and Payment Security
137–049–0470
Substitute Contractor
137–049–0490
Foreign Contractor
137–049–0600
Purpose
137–049–0610
Definitions for Alternative Contracting Methods
137–049–0620
Use of Alternative Contracting Methods
137–049–0630
Findings, Notice and Hearing
137–049–0640
Competitive Proposals
137–049–0645
Requests for Qualifications (RFQ)
137–049–0650
Requests for Proposals (“RFP”)
137–049–0660
RFP Pricing Mechanisms
137–049–0670
Design-Build Contracts
137–049–0680
Energy Savings Performance Contracts (ESPC)
137–049–0690
Construction Manager/General Contractor Services (“CM/GC Services”)
137–049–0800
Required Contract Clauses
137–049–0810
Waiver of Delay Damages Against Public Policy
137–049–0815
BOLI Public Works Bond
137–049–0820
Retainage
137–049–0830
Contractor Progress Payments
137–049–0840
Interest
137–049–0850
Final Inspection
137–049–0860
Public Works Contracts
137–049–0870
Specifications
137–049–0880
Records Maintenance
137–049–0890
Contracting Agency Payment for Unpaid Labor or Supplies
137–049–0900
Contract Suspension
137–049–0910
Changes to the Work and Contract Amendments
Last Updated

Jun. 24, 2021

Rule 137-049-0680’s source at or​.us