OAR 330-068-0020
Program Procedures


(1)

Energy auditor training: The Department shall provide to representatives of institutions (except for facilities other than buildings), energy auditor training or orientation which meets guidelines and standards provided by Bonneville. The Department shall certify individuals as energy auditors in accordance with procedures approved by Bonneville.

(2)

Energy audit: The Department shall provide, at no direct cost to an institution, a list of energy auditors and model forms for use in conducting energy audits (for buildings and occupied buildings only).

(3)

Technical assistance studies (TAS):

(a)

The Department shall solicit, evaluate, rank, and select for funding applications for TASs. Ranking shall be in accordance with OAR 330-068-0085 (Project Ranking Formula)(1). The Department shall notify applicants in writing whether or not they have been selected for funding;

(b)

The Department shall ensure that the requirements in paragraphs (A), through (E) of this subsection, are met before disbursing funds for a TAS (for buildings and occupied buildings only):

(A)

An energy audit has been completed by an ODOE certified energy auditor;

(B)

All O&M activities identified in the energy audit have been implemented by the institution, except those which the Department determines, in accordance with guidelines and environmental restrictions provided by Bonneville, need not be implemented;

(C)

The institution has solicited qualifications of licensed engineers or licensed architect-engineer teams for accomplishing the TAS before choosing a licensed engineer or licensed architect-engineer team, unless otherwise agreed to by the Department and such Institution;

(D)

The TAS has been performed by a licensed engineer or licensed architect-engineer team, and has been reviewed and approved by the Department;

(E)

The institution provides the Department with proof of payment to the licensed engineer or architect-engineer team of all agreed upon costs for performing the technical assistance study.

(c)

The Department shall ensure that the requirements in paragraphs (A) through (D) of this subsection are met before disbursing funds for a TAS (for facilities other than buildings):

(A)

All O&M activities identified in the facilities TAS have been implemented by the institution, except those which the Department determines, in accordance with guidelines and environmental restrictions provided by Bonneville, need not be implemented;

(B)

The institution has solicited qualifications of licensed engineers or licensed architect-engineer teams, with at least one year of documented experience in the design or operation of the particular facility other than a building being studied, for accomplishing the TAS before choosing a licensed engineer or licensed architect-engineer team, unless otherwise agreed to by the Department and such institution;

(C)

The TAS has been performed by a licensed engineer or licensed architect-engineer team and has been reviewed and approved by the Department;

(D)

The Institution provides the Department with proof of payment to a licensed engineer or architect-engineer team of all agreed upon costs for performing the technical assistance study.

(d)

The Department shall pay an Institution 50 percent of the amount determined in accordance with the TAS payment formula in rule 330-068-0090 (Payment Levels), upon completion of the TAS in accordance with the above requirements. The Department shall pay the institution the remaining 50 percent of the TAS amount when the conditions in either of paragraphs (A) or (B) of this subsection are met:

(A)

The Institution installs, at its own expense, ECMs recommended in the TAS, the total cost of which is at least equal to the remaining 50 percent of the TAS amount;

(B)

The institution agrees in writing to install, upon approval of funding, ECMs recommended in the TAS, the total cost of which is at least equal to the remaining 50 percent of the TAS amount. If an institution which has received the remaining 50 percent of the TAS amount, or any portion thereof, does not install such ECMs upon approval of funding, the Department shall require the institution to return the payment for the remaining 50 percent of such institution’s TAS amount, or any portion thereof received, to the Department;

(C)

The Department shall not pay the institution the total remaining 50 percent of its TAS if one of either condition in paragraph (A) or (B) of this subsection is not satisfied and if:
(i)
The TAS does not recommend any eligible electrical ECMs even though its TAS does satisfy the requirements as stated in subsections (3)(b) and (c) of this rule;
(ii)
The total cost of the recommended eligible electrical ECMs does not equal the remaining 50 percent of the TAS amount, even though the TAS does satisfy the requirements as stated in subsections (3)(b) and (c) of this rule.

(4)

Energy conservation measures (ECMs):

(a)

The Department shall solicit, evaluate, and select Projects for funding at least once but not more than four times annually. The Department shall notify applicants in writing whether or not they have been selected for funding;

(b)

The Department shall comply with the procedures in paragraphs (A) through (E) of this subsection prior to approving a Project application for funding:

(A)

The Department shall provide a licensed professional engineer, other than the engineer or architect-engineer team who performed the TAS, to review and certify that energy savings and project cost estimates of ECMs recommended in the TAS were calculated using standard engineering practices, and that only ECMs recommended in a TAS are included in a project;

(B)

The Department shall rank and select for funding projects in accordance with the ranking formula for ECM’s found in OAR 330-068-0085 (Project Ranking Formula)(2)(a), if requests for project funding exceed the portion of the approved budget approved for ECMs;

(C)

The Department shall ensure that the following conditions will not occur as a result of project installation:
(i)
Installation of low-pressure sodium vapor lights indoors;
(ii)
Use of toxic transfer fluids in solar heating systems;
(iii)
Use of high pressure sodium vapor lights indoors except for:

(I)

General lighting in warehouses with low visual demand activities and short duration occupancies; and for

(II)

High visual demand lighting in high bay areas, as defined by IES Lighting Handbook, where the mixture of HPS to incandescent, fluorescent, or metal halide fixtures is at least 1-to-1 with similar lumen output from both types of fixtures and the HPS fixtures are staggered on a multiple phase circuitry.
(iv)
Removal or disturbance of previously installed asbestos;
(v)
Installation of Urea Formaldehyde Foam Insulation (UFFI).

(D)

The Department shall ensure that Bonneville funds are not used to pay for ECM’s which Bonneville has determined are environmentally restricted;

(E)

The Department shall obtain from the institution a written agreement to indemnify Bonneville and hold it harmless from and against all claims and liability and expenses, including reasonable attorneys fees, arising from the negligent or other tortious acts or omissions of the Institution’s officers, agents, or employes.

(c)

The Department shall comply with the procedures in paragraphs (A) through (D) of this subsection, prior to disbursing funds to institutions for completed projects:

(A)

For projects that require the preparation of design documents by, or have had design documents prepared by a licensed professional engineer, a licensed architect or licensed architect-engineer team, the Department shall provide a licensed professional engineer, other than the engineer, architect or architect-engineer team who prepared the design documents, to review and verify prior to bid release, that the project design has been prepared in accordance with standard engineering practice and can reasonably be expected to produce the energy savings identified for the project in the TAS;

(B)

The Department shall ensure that the institution has solicited three competitive bids for ECM installations unless otherwise agreed to by the Department and the institution, and has chosen an installer on the basis of price and capability;

(C)

The Department shall inspect each project for proper and complete installation of ECMs and confirm such installation in writing in accordance with the following:
(i)
Projects that require the preparation of design documents by, or have had design documents prepared by a licensed professional engineer, a licensed architect or licensed architect-engineer team (except that projects involving the installation of insulation, windows, doors and lighting will not require inspection by a professional engineer), shall be inspected by a licensed professional engineer other than a licensed professional engineer, licensed architect or licensed architect-engineer team installing ECMs as part of such project; and
(ii)
Projects that do not require professional design work, or any project involving the installation of insulation, windows, doors and lighting, shall be inspected by an inspector with qualifications approved by Bonneville.

(D)

The Department shall obtain from the institution proof of final payment of all agreed upon costs for ECM installations.

(d)

The Department shall pay an institution in accordance with OAR 330-068-0090 (Payment Levels) for installed ECMs.

(5)

Performance bond. A performance bond shall be furnished and maintained in the amount of 100 percent of the project amount when the project amount exceeds $10,000 and when the Department has authorized progress payments for such project.

(6)

The Department may limit the amount of TAS or ECM funding any single institution may receive, so long as such limitations do not result in unreasonable discrimination. Eligible institutions shall be notified of funding limitations at the beginning of each program cycle.