OAR 629-605-0173
Plans for an Alternate Practice
(1)
Operators must obtain written approval of a plan for an alternate practice from the State Forester before conducting forest practices utilizing protection standards or methods different than those specified in rule or statute.(2)
Plans for an alternate practice must include sufficient information to allow the State Forester to assess the plan to determine that the practices described in the plan will yield results consistent with ORS 527.610 (Short title) to 527.770 (Good faith compliance with best management practices not violation of water quality standards) and administrative rules adopted thereunder.(3)
Plans for alternate practices proposed as part of a written plan required by ORS 527.670 (Commencement of operations)(3) shall be subject to the hearings provisions of 527.700 (Appeals from orders of State Forester)(3) (Appeals from orders of State Forester hearings procedure; stay of operation); and shall be subject to the provisions of 527.670 (Commencement of operations)(10), (11) and (12) (Commencement of operations; when notice and written plan required; appeal of plan) prescribing certain waiting periods and procedures.(4)
An operator must comply with all provisions of an approved plan for an alternate practice.(5)
The following rules require an operator to submit a plan for an alternate practice and obtain approval from the State Forester of the plan before starting the specified practice or operation:
Source:
Rule 629-605-0173 — Plans for an Alternate Practice, https://secure.sos.state.or.us/oard/view.action?ruleNumber=629-605-0173
.