OAR 731-005-0680
Rejection of All Offers


(1)

Rejection. ODOT may reject all Offers for good cause upon ODOT’s Written finding it is in the public interest to do so. ODOT shall notify all Offerors of the rejection of all Offers, along with the good cause justification and finding.

(2)

Criteria. ODOT may reject all Offers upon a Written finding that:

(a)

The content of or an error in the Solicitation Document, or the solicitation process unnecessarily restricted competition for the Contract;

(b)

The price, quality or performance presented by the Offerors is too costly or of insufficient quality to justify acceptance of the Offer;

(c)

Misconduct, error, or ambiguous or misleading provisions in the Solicitation Document threaten the fairness and integrity of the competitive process;

(d)

Causes other than legitimate market forces threaten the integrity of the competitive procurement process. These causes include, but are not limited to, those that tend to limit competition such as restrictions on competition, collusion, corruption, unlawful anti-competitive conduct, and inadvertent or intentional errors in the Solicitation Document;

(e)

ODOT cancels the solicitation in accordance with OAR 731-005-0720 (Cancellation of Solicitation); or

(f)

Any other circumstance indicating that awarding the Contract would not be in the public interest.

Source: Rule 731-005-0680 — Rejection of All Offers, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=731-005-0680.

731–005–0400
Repealed Rules
731–005–0410
Effective Date
731–005–0420
Scope
731–005–0430
Definitions
731–005–0440
Competitive Procurement
731–005–0460
Eligibility to Bid or Propose on Construction or Landscape Contracts
731–005–0470
Solicitation Methods
731–005–0480
Brand Name Products
731–005–0490
Bids or Proposals Are Offers
731–005–0500
Facsimile Bids and Proposals
731–005–0505
Electronic Procurement
731–005–0510
Use of Electronic Data Interchange
731–005–0520
Notice and Advertising Requirements
731–005–0530
Offer Preparation
731–005–0540
Offeror Submissions
731–005–0550
Bid or Proposal Security
731–005–0560
Pre-Offer Conferences
731–005–0570
Solicitation Protest
731–005–0580
Addenda to a Solicitation Document
731–005–0590
Pre-Opening Modification or Withdrawal of Offers
731–005–0600
Receipt, Opening, and Recording of Offers
731–005–0610
Late Offers, Late Withdrawals and Late Modifications
731–005–0620
Mistakes
731–005–0630
Time for Agency Acceptance
731–005–0640
Extension of Time for Acceptance of Offer
731–005–0650
Offer Evaluation and Award
731–005–0660
Tie Offers
731–005–0670
Rejection of an Offer
731–005–0680
Rejection of All Offers
731–005–0690
Protest of Contractor Selection, Contract Award
731–005–0700
Negotiation with Bidders
731–005–0710
Disqualification of an Entity
731–005–0720
Cancellation of Solicitation
731–005–0730
Disposition of Offers if Solicitation Canceled
731–005–0740
Documentation of Award
731–005–0750
Non-Resident Contractor
731–005–0760
Availability of Award Decisions
731–005–0770
Performance Security
Last Updated

Jun. 8, 2021

Rule 731-005-0680’s source at or​.us