OAR 860-024-0021
Liquefied Natural Gas Safety


Every gas operator must construct, operate, and maintain liquefied natural gas facilities in compliance with the standards prescribed by:

(1)

49 CFR, Part 191, and amendments through No. 25 — Transportation of Natural and Other Gas by Pipeline; Annual Reports and Incident Reports in effect on March 24, 2017.

(2)

49 CFR, Part 193, and amendments through No. 25 — Liquefied Natural Gas Facilities; Minimum Safety Standards in effect on March 6, 2015.

(3)

49 CFR, Part 199, and amendments through No. 27 — Control of Drug and Alcohol Use in Natural Gas, Liquefied Natural Gas, and Hazardous Liquid Pipeline Operations in effect on March 24, 2017.

(4)

49 CFR, Part 40, and amendments through No. 29 – Procedure for Transportation Workplace Drug and Alcohol Testing Programs in effect on October 3, 2012.
[Publications: Publications referenced are available from the agency.]

Source: Rule 860-024-0021 — Liquefied Natural Gas Safety, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-024-0021.

860–024–0000
Applicability of Division 24
860–024–0001
Definitions for Safety Standards
860–024–0005
Maps and Records
860–024–0007
Location of Underground Facilities
860–024–0010
Construction, Operation, and Maintenance of Electrical Supply and Communication Lines
860–024–0011
Inspections of Electric Supply and Communication Facilities
860–024–0012
Prioritization of Repairs by Operators of Electric Supply Facilities and Operators of Communication Facilities
860–024–0015
Ground Return
860–024–0016
Minimum Vegetation Clearance Requirements
860–024–0017
Vegetation Pruning Standards
860–024–0020
Gas Pipeline Safety
860–024–0021
Liquefied Natural Gas Safety
860–024–0025
Steam Heat — Construction, Operation, and Maintenance of Steam and Hot Water Transmission and Distribution Systems
860–024–0050
Incident Reports
860–024–0060
Definitions for Public Safety Power Shutoff
860–024–0070
Requirement to Notify for Public Safety Power Shutoff
860–024–0080
Procedure for Notification for Public Safety Power Shutoff
860–024–0090
Required Information in Notifications in Advance of and Directly Preceding a De-Energization Event for Public Safety Power Shutoff
860–024–0100
Points of Contact for Public Safety Power Shutoff
860–024–0110
Methods for Communicating De-Energization Event with the Public for Public Safety Power Shutoff
860–024–0120
Coordination with Public Safety Partners Before and During a De-Energization Event for Public Safety Power Shutoff
860–024–0130
Coordination with Emergency Response Centers and Incident Command Systems for Public Safety Power Shutoff
860–024–0140
Request to Delay De-Energization for Public Safety Power Shutoff
860–024–0150
De-Energization of Transmission Lines for Public Safety Power Shutoff
860–024–0160
Reporting Requirements for Public Safety Power Shutoff
Last Updated

Jun. 8, 2021

Rule 860-024-0021’s source at or​.us