OAR 860-024-0140
Request to Delay De-Energization for Public Safety Power Shutoff


(1) The Electric Utility should address requests for a de-energization delay on a case-by-case basis when requests are made from Public Safety Partner. The Electric Utility retains ultimate authority to grant a delay and responsibility to determine how a delay in de-energization impacts public safety.
(2) If the Electric Utility receives a request to delay de-energization, it must notify the Commission ESF-12 liaison of the request, the reason for the request, the utility’s decision, and justification for the decision within two hours of the request.

Source: Rule 860-024-0140 — Request to Delay De-Energization for Public Safety Power Shutoff, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-024-0140.

860‑024‑0000
Applicability of Division 24
860‑024‑0001
Definitions for Safety Standards
860‑024‑0005
Maps and Records
860‑024‑0007
Location of Underground Facilities
860‑024‑0010
Construction, Operation, and Maintenance of Electrical Supply and Communication Lines
860‑024‑0011
Inspections of Electric Supply and Communication Facilities
860‑024‑0012
Prioritization of Repairs by Operators of Electric Supply Facilities and Operators of Communication Facilities
860‑024‑0015
Ground Return
860‑024‑0016
Minimum Vegetation Clearance Requirements
860‑024‑0017
Vegetation Pruning Standards
860‑024‑0020
Gas Pipeline Safety
860‑024‑0021
Liquefied Natural Gas Safety
860‑024‑0025
Steam Heat — Construction, Operation, and Maintenance of Steam and Hot Water Transmission and Distribution Systems
860‑024‑0050
Incident Reports
860‑024‑0060
Definitions for Public Safety Power Shutoff
860‑024‑0070
Requirement to Notify for Public Safety Power Shutoff
860‑024‑0080
Procedure for Notification for Public Safety Power Shutoff
860‑024‑0090
Required Information in Notifications in Advance of and Directly Preceding a De-Energization Event for Public Safety Power Shutoff
860‑024‑0100
Points of Contact for Public Safety Power Shutoff
860‑024‑0110
Methods for Communicating De-Energization Event with the Public for Public Safety Power Shutoff
860‑024‑0120
Coordination with Public Safety Partners Before and During a De-Energization Event for Public Safety Power Shutoff
860‑024‑0130
Coordination with Emergency Response Centers and Incident Command Systems for Public Safety Power Shutoff
860‑024‑0140
Request to Delay De-Energization for Public Safety Power Shutoff
860‑024‑0150
De-Energization of Transmission Lines for Public Safety Power Shutoff
860‑024‑0160
Reporting Requirements for Public Safety Power Shutoff
Last Updated

Jun. 8, 2021

Rule 860-024-0140’s source at or​.us