OAR 860-084-0230
Application for Capacity Reservation


(1)

The electric company must establish, in compliance with Commission order, a capacity application process for both the net metering and competitive bidding options. The electric company must provide the necessary instructions to complete a satisfactory capacity application. Fees collected during the capacity application process must be refunded to the retail electricity consumer if a capacity reservation is not secured.

(2)

For the purposes of these rules, an application package must include a capacity reservation application, payment of fees required under OAR 860-084-0280 (Interconnection Cost Responsibility), and an interconnection application that complies with 860-084-0270 (Authorization to Interconnect)(4)(a), (c), (d), (f), and (g). Electric companies may not require a retail electricity consumer to provide the information required by 860-084-0270 (Authorization to Interconnect)(4)(b) and (4)(e) as part of this initial application package.

(3)

The capacity reservation application must certify that the retail electricity consumer has read and understands the standard contract established under the pilot program. Standard contract forms must be provided to retail electricity consumers as part of the application process.

Source: Rule 860-084-0230 — Application for Capacity Reservation, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-084-0230.

860‑084‑0000
Scope and Applicability of Solar Photovoltaic Programs
860‑084‑0010
Definitions for Solar Photovoltaic Pilot Programs
860‑084‑0070
Renewable Energy Certificates and Compliance with the Renewable Portfolio Standards
860‑084‑0100
Solar Photovoltaic Pilot Programs
860‑084‑0120
Systems Eligible for Enrollment in Pilot Programs
860‑084‑0130
Ownership and Installation
860‑084‑0140
Assignment of Payments
860‑084‑0150
Solar Photovoltaic Pilot Capacity Limit
860‑084‑0160
Measurement of Capacity under the Solar Photovoltaic Pilot Program
860‑084‑0170
Distributing Solar Photovoltaic Pilot Capacity by Electric Company
860‑084‑0180
Distributing Electric Company Capacity Limit by Allocation Period
860‑084‑0190
Distributing Capacity by System Size
860‑084‑0195
Mechanisms for Reserving Capacity
860‑084‑0200
Capacity Reservation, Timing, and Volumetric Incentive Rates
860‑084‑0210
Capacity Reservation, Timing, and Duration
860‑084‑0220
Capacity Availability
860‑084‑0230
Application for Capacity Reservation
860‑084‑0240
Standard Contracts
860‑084‑0250
Billing and Payment Requirements
860‑084‑0260
Interconnection Requirements for Solar Photovoltaic Pilot Program
860‑084‑0270
Authorization to Interconnect
860‑084‑0280
Interconnection Cost Responsibility
860‑084‑0300
Insurance
860‑084‑0310
Level 1 System Interconnection Review
860‑084‑0320
Level 2 System Interconnection Review
860‑084‑0330
Level 3 System Interconnection Review
860‑084‑0340
Installation, Operation, Maintenance, and Testing of Contracted Systems
860‑084‑0350
Requirements after Approval of a Solar Photovoltaic Interconnection
860‑084‑0360
Volumetric Incentive Rates and Payments – Net Metering Option
860‑084‑0365
Volumetric Incentive Rate Bidding Option
860‑084‑0370
Resource Value
860‑084‑0380
Cost Recovery and Rate Impacts
860‑084‑0390
Cost Recovery Mechanism
860‑084‑0400
Data Collection
860‑084‑0420
Compliance with Pilot Program Requirements
860‑084‑0430
Data Availability
860‑084‑0440
Pilot Program Overhead
860‑084‑0450
Reports to the Legislature
Last Updated

Jun. 8, 2021

Rule 860-084-0230’s source at or​.us