OAR 860-084-0280
Interconnection Cost Responsibility


(1)

For a Level 1 interconnection review, the electric company may not charge an application, or other fee, unless otherwise directed by the Commission. However, if an application for Level 1 interconnection review is denied because it does not meet the requirements for Level 1 interconnection review and the applicant resubmits the application under another review procedure, the electric company may impose a fee for the resubmitted application.

(2)

For a Level 2 interconnection review, the electric company may charge fees of up to $50.00 plus $1.00 per kilowatt of the qualifying system’s capacity, plus the reasonable cost of any required minor modifications to the electric distribution system or additional review. Costs for such minor modifications or additional review will be based on the electric company’s non-binding, good faith estimates and the ultimate actual installed costs. Costs for engineering work done as part of any additional review will not exceed $100.00 per hour. An electric company may adjust the $100.00 hourly rate once in January of each year to account for inflation and deflation as measured by the Consumer Price Index.

(3)

For a Level 3 interconnection review, the electric company may charge fees of up to $100.00 plus $2.00 per kilowatt of the qualifying system’s capacity, as well as charges for actual time spent on any required impact or facilities studies. Costs for engineering work done as part of an impact study or interconnection facilities study will not exceed $100.00 per hour. An electric company may adjust the $100.00 hourly rate once in January of each year to account for inflation and deflation as measured by the Consumer Price Index. If the electric company must install facilities in order to accommodate the interconnection of the qualifying system, the cost of such facilities will be the responsibility of the applicant.

(4)

Interconnected net metered systems must be equipped with two meters: metering equipment that can measure the flow of electricity in both directions (complying with ANSI C12.1 standards and OAR 860-023-0015 (Testing Gas and Electric Meters)) to replace the existing customer meter, and a second meter that can measure the total output of the qualifying system. Interconnected stand-alone systems using the bidding process must be equipped with metering equipment that can measure the flow of electricity in both directions (complying with ANSI C12.1 standards and OAR 860-023-0015 (Testing Gas and Electric Meters)). The electric company will install the required metering equipment at the electric company’s expense for both the net metered and stand-alone system.

(a)

The electric company constructs, owns, operates, and maintains all meters and applicable interconnection facilities on the company side of the retail electric consumer’s meter, including, the second meter installed to measure the total output of the qualifying system.

(b)

The electric company must charge an additional monthly service charge to the retail electricity customer for the additional meter used to measure the total output of the qualifying system, as established by Commission order.

(5)

An eligible participant who is reinstalling a contracted system and is eligible to continue in the solar photovoltaic pilot program under an existing standard contract must pay the expense of interconnection facilities, required additions or modifications to the electric distribution system, interconnection review, or system upgrades in the new location as applicable.

Source: Rule 860-084-0280 — Interconnection Cost Responsibility, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-084-0280.

860‑084‑0000
Scope and Applicability of Solar Photovoltaic Programs
860‑084‑0010
Definitions for Solar Photovoltaic Pilot Programs
860‑084‑0070
Renewable Energy Certificates and Compliance with the Renewable Portfolio Standards
860‑084‑0100
Solar Photovoltaic Pilot Programs
860‑084‑0120
Systems Eligible for Enrollment in Pilot Programs
860‑084‑0130
Ownership and Installation
860‑084‑0140
Assignment of Payments
860‑084‑0150
Solar Photovoltaic Pilot Capacity Limit
860‑084‑0160
Measurement of Capacity under the Solar Photovoltaic Pilot Program
860‑084‑0170
Distributing Solar Photovoltaic Pilot Capacity by Electric Company
860‑084‑0180
Distributing Electric Company Capacity Limit by Allocation Period
860‑084‑0190
Distributing Capacity by System Size
860‑084‑0195
Mechanisms for Reserving Capacity
860‑084‑0200
Capacity Reservation, Timing, and Volumetric Incentive Rates
860‑084‑0210
Capacity Reservation, Timing, and Duration
860‑084‑0220
Capacity Availability
860‑084‑0230
Application for Capacity Reservation
860‑084‑0240
Standard Contracts
860‑084‑0250
Billing and Payment Requirements
860‑084‑0260
Interconnection Requirements for Solar Photovoltaic Pilot Program
860‑084‑0270
Authorization to Interconnect
860‑084‑0280
Interconnection Cost Responsibility
860‑084‑0300
Insurance
860‑084‑0310
Level 1 System Interconnection Review
860‑084‑0320
Level 2 System Interconnection Review
860‑084‑0330
Level 3 System Interconnection Review
860‑084‑0340
Installation, Operation, Maintenance, and Testing of Contracted Systems
860‑084‑0350
Requirements after Approval of a Solar Photovoltaic Interconnection
860‑084‑0360
Volumetric Incentive Rates and Payments – Net Metering Option
860‑084‑0365
Volumetric Incentive Rate Bidding Option
860‑084‑0370
Resource Value
860‑084‑0380
Cost Recovery and Rate Impacts
860‑084‑0390
Cost Recovery Mechanism
860‑084‑0400
Data Collection
860‑084‑0420
Compliance with Pilot Program Requirements
860‑084‑0430
Data Availability
860‑084‑0440
Pilot Program Overhead
860‑084‑0450
Reports to the Legislature
Last Updated

Jun. 8, 2021

Rule 860-084-0280’s source at or​.us