OAR 860-084-0440
Pilot Program Overhead


(1)

Electric companies must submit for Commission approval evaluations of solar photovoltaic pilot programs including:

(a)

Proposals for the design and execution of surveys to measure participant satisfaction with and recommendations for improving the pilot program processes;

(b)

Proposals for the design and execution of surveys to understand participant decision processes in choosing between the volumetric incentive rate program and the existing net metering program;

(c)

Comments on Commission recommendations for regulatory policy changes that may increase the use of solar photovoltaic systems, make solar photovoltaic systems more affordable, reduce the cost of incentives to utility customers, or promote the development of the solar industry in Oregon; and

(d)

Additions to the list of required data to be collected under OAR 860-084-0400 (Data Collection).

(2)

Each electric company may enter into a contract with the Energy Trust of Oregon to provide the data collection and summary services required by OAR 860-084-0400 (Data Collection) through 860-084-0440 (Pilot Program Overhead). An electric company may also contract with the Energy Trust of Oregon to administer pilot programs, including capacity reservation services, survey execution, or program evaluation. The Commission may direct the electric companies to contract with the Energy Trust of Oregon if the Commission finds that the costs to administer individual pilot programs are unreasonable.

Source: Rule 860-084-0440 — Pilot Program Overhead, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-084-0440.

860‑084‑0000
Scope and Applicability of Solar Photovoltaic Programs
860‑084‑0010
Definitions for Solar Photovoltaic Pilot Programs
860‑084‑0070
Renewable Energy Certificates and Compliance with the Renewable Portfolio Standards
860‑084‑0100
Solar Photovoltaic Pilot Programs
860‑084‑0120
Systems Eligible for Enrollment in Pilot Programs
860‑084‑0130
Ownership and Installation
860‑084‑0140
Assignment of Payments
860‑084‑0150
Solar Photovoltaic Pilot Capacity Limit
860‑084‑0160
Measurement of Capacity under the Solar Photovoltaic Pilot Program
860‑084‑0170
Distributing Solar Photovoltaic Pilot Capacity by Electric Company
860‑084‑0180
Distributing Electric Company Capacity Limit by Allocation Period
860‑084‑0190
Distributing Capacity by System Size
860‑084‑0195
Mechanisms for Reserving Capacity
860‑084‑0200
Capacity Reservation, Timing, and Volumetric Incentive Rates
860‑084‑0210
Capacity Reservation, Timing, and Duration
860‑084‑0220
Capacity Availability
860‑084‑0230
Application for Capacity Reservation
860‑084‑0240
Standard Contracts
860‑084‑0250
Billing and Payment Requirements
860‑084‑0260
Interconnection Requirements for Solar Photovoltaic Pilot Program
860‑084‑0270
Authorization to Interconnect
860‑084‑0280
Interconnection Cost Responsibility
860‑084‑0300
Insurance
860‑084‑0310
Level 1 System Interconnection Review
860‑084‑0320
Level 2 System Interconnection Review
860‑084‑0330
Level 3 System Interconnection Review
860‑084‑0340
Installation, Operation, Maintenance, and Testing of Contracted Systems
860‑084‑0350
Requirements after Approval of a Solar Photovoltaic Interconnection
860‑084‑0360
Volumetric Incentive Rates and Payments – Net Metering Option
860‑084‑0365
Volumetric Incentive Rate Bidding Option
860‑084‑0370
Resource Value
860‑084‑0380
Cost Recovery and Rate Impacts
860‑084‑0390
Cost Recovery Mechanism
860‑084‑0400
Data Collection
860‑084‑0420
Compliance with Pilot Program Requirements
860‑084‑0430
Data Availability
860‑084‑0440
Pilot Program Overhead
860‑084‑0450
Reports to the Legislature
Last Updated

Jun. 8, 2021

Rule 860-084-0440’s source at or​.us