OAR 860-084-0260
Interconnection Requirements for Solar Photovoltaic Pilot Program


(1)

To be qualified for interconnected operation, a qualifying system must be certified as complying with the following standards as applicable:

(a)

IEEE standards; and

(b)

UL 1741 Inverters, Converters, and Controllers for Use in Independent Power Systems (January 2001).

(2)

A system is considered as certified to the standards of section (1) of this rule, and the electric company may not require further design review, testing, or additional equipment, if:

(a)

The system is a complete equipment package that has been submitted by a manufacturer to a nationally recognized testing and certification laboratory, and has been tested and listed by the laboratory for continuous interactive operation with an electric distribution system in compliance with the applicable codes and standards listed in section (1) of this rule; or

(b)

The system is an equipment package that includes a generator or other electric source and the equipment package has been tested and listed as an integrated package in compliance with the applicable codes and standards listed in section (1) of this rule; or

(c)

The certified equipment package comprises only the interface components (switchgear, inverters, or other interface devices), and the interconnection applicant has shown that

(A)

The solar photovoltaic system being used is compatible with the equipment package;

(B)

Testing and listing of the solar photovoltaic generator being used, as performed by the nationally recognized testing and certification laboratory, is consistent with the testing and listing of the interface component equipment package; and

(C)

The testing and listing specified for the package is consistent with the applicable codes and standards listed in section (1) of this rule.

(3)

A qualifying system may not interconnect to a transmission line.

Source: Rule 860-084-0260 — Interconnection Requirements for Solar Photovoltaic Pilot Program, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-084-0260.

860‑084‑0000
Scope and Applicability of Solar Photovoltaic Programs
860‑084‑0010
Definitions for Solar Photovoltaic Pilot Programs
860‑084‑0070
Renewable Energy Certificates and Compliance with the Renewable Portfolio Standards
860‑084‑0100
Solar Photovoltaic Pilot Programs
860‑084‑0120
Systems Eligible for Enrollment in Pilot Programs
860‑084‑0130
Ownership and Installation
860‑084‑0140
Assignment of Payments
860‑084‑0150
Solar Photovoltaic Pilot Capacity Limit
860‑084‑0160
Measurement of Capacity under the Solar Photovoltaic Pilot Program
860‑084‑0170
Distributing Solar Photovoltaic Pilot Capacity by Electric Company
860‑084‑0180
Distributing Electric Company Capacity Limit by Allocation Period
860‑084‑0190
Distributing Capacity by System Size
860‑084‑0195
Mechanisms for Reserving Capacity
860‑084‑0200
Capacity Reservation, Timing, and Volumetric Incentive Rates
860‑084‑0210
Capacity Reservation, Timing, and Duration
860‑084‑0220
Capacity Availability
860‑084‑0230
Application for Capacity Reservation
860‑084‑0240
Standard Contracts
860‑084‑0250
Billing and Payment Requirements
860‑084‑0260
Interconnection Requirements for Solar Photovoltaic Pilot Program
860‑084‑0270
Authorization to Interconnect
860‑084‑0280
Interconnection Cost Responsibility
860‑084‑0300
Insurance
860‑084‑0310
Level 1 System Interconnection Review
860‑084‑0320
Level 2 System Interconnection Review
860‑084‑0330
Level 3 System Interconnection Review
860‑084‑0340
Installation, Operation, Maintenance, and Testing of Contracted Systems
860‑084‑0350
Requirements after Approval of a Solar Photovoltaic Interconnection
860‑084‑0360
Volumetric Incentive Rates and Payments – Net Metering Option
860‑084‑0365
Volumetric Incentive Rate Bidding Option
860‑084‑0370
Resource Value
860‑084‑0380
Cost Recovery and Rate Impacts
860‑084‑0390
Cost Recovery Mechanism
860‑084‑0400
Data Collection
860‑084‑0420
Compliance with Pilot Program Requirements
860‑084‑0430
Data Availability
860‑084‑0440
Pilot Program Overhead
860‑084‑0450
Reports to the Legislature
Last Updated

Jun. 8, 2021

Rule 860-084-0260’s source at or​.us