OAR 860-084-0310
Level 1 System Interconnection Review


(1)

An eligible system is eligible for Level 1 interconnection review if:

(a)

The facility is inverter-based; and

(b)

The facility has a capacity of 25 kilowatts or less.

(2)

The electric company must approve interconnection under the Level 1 interconnection review procedure if:

(a)

The aggregate generation capacity on the distribution circuit to which the eligible system will interconnect, including the capacity of the eligible system, may not contribute more than 10 percent to the distribution circuit’s maximum fault current at the point on the high voltage (primary) level that is nearest the proposed point of common coupling;

(b)

An eligible system’s point of common coupling may not be on a transmission line, a spot network, or an area network;

(c)

If an eligible system is to be connected to a radial distribution circuit, the aggregate generation capacity connected to the circuit, including that of the eligible system, may not exceed 15 percent of the circuit’s total annual peak load, as most recently measured at the substation;

(d)

If an eligible system is to be connected to a single-phase shared secondary, the aggregate generation capacity connected to the shared secondary, including the eligible system, may not exceed 20 kilovolt-amps; and

(e)

If a single-phase eligible system is to be connected to a transformer center tap neutral of a 240 volt service, the addition of the eligible system may not create a current imbalance between the two sides of the 240 volt service of more than 20 percent of nameplate rating of the service transformer.

(3)

Within 10 business days after the electric company notifies a Level 1 applicant that the application is complete, the electric company must notify the applicant that:

(a)

The eligible system meets all applicable criteria and the interconnection is approved upon installation of any required meter upgrade, completion of any required inspection of the facility, and execution of an interconnection agreement; or

(b)

The eligible system has failed to meet one or more of the applicable criteria and the interconnection application is denied.

(4)

If an electric company does not notify a Level 1 applicant in writing or by electronic mail whether the interconnection is approved or denied within 20 business days after the receipt of an application, the interconnection will be deemed approved. Interconnections approved under this section remain subject to section (7) of this rule.

(5)

Within three business days after sending the notice to an applicant that the proposed interconnection meets the Level 1 requirements, an electric company must notify the applicant:

(a)

Whether an inspection of the eligible system for compliance with these interconnection rules is required prior to the operation of the system; and

(b)

That an interconnection agreement is required for the eligible system. The electric company must also execute and send to the applicant a Level 1 interconnection agreement, unless the applicant has already submitted such an agreement with its application for interconnection.

(6)

On receipt of an executed interconnection agreement from the applicant and satisfactory completion of any required inspection, the electric company must approve the interconnection, conditioned on compliance with all applicable building codes.

(7)

The retail electric customer must notify the electric company of the anticipated start date for operation of the eligible system at least five business days prior to starting operation, either through the submittal of the interconnection agreement or in a separate notice. If the electric company requires an inspection of the eligible system, the applicant may not begin operating the facility until satisfactory completion of the inspection.

(8)

If an application for Level 1 interconnection review is denied because it does not meet one or more of the applicable requirements in this rule, an applicant may resubmit the application under the Level 2 or Level 3 interconnection review procedure, as appropriate.

Source: Rule 860-084-0310 — Level 1 System Interconnection Review, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-084-0310.

860‑084‑0000
Scope and Applicability of Solar Photovoltaic Programs
860‑084‑0010
Definitions for Solar Photovoltaic Pilot Programs
860‑084‑0070
Renewable Energy Certificates and Compliance with the Renewable Portfolio Standards
860‑084‑0100
Solar Photovoltaic Pilot Programs
860‑084‑0120
Systems Eligible for Enrollment in Pilot Programs
860‑084‑0130
Ownership and Installation
860‑084‑0140
Assignment of Payments
860‑084‑0150
Solar Photovoltaic Pilot Capacity Limit
860‑084‑0160
Measurement of Capacity under the Solar Photovoltaic Pilot Program
860‑084‑0170
Distributing Solar Photovoltaic Pilot Capacity by Electric Company
860‑084‑0180
Distributing Electric Company Capacity Limit by Allocation Period
860‑084‑0190
Distributing Capacity by System Size
860‑084‑0195
Mechanisms for Reserving Capacity
860‑084‑0200
Capacity Reservation, Timing, and Volumetric Incentive Rates
860‑084‑0210
Capacity Reservation, Timing, and Duration
860‑084‑0220
Capacity Availability
860‑084‑0230
Application for Capacity Reservation
860‑084‑0240
Standard Contracts
860‑084‑0250
Billing and Payment Requirements
860‑084‑0260
Interconnection Requirements for Solar Photovoltaic Pilot Program
860‑084‑0270
Authorization to Interconnect
860‑084‑0280
Interconnection Cost Responsibility
860‑084‑0300
Insurance
860‑084‑0310
Level 1 System Interconnection Review
860‑084‑0320
Level 2 System Interconnection Review
860‑084‑0330
Level 3 System Interconnection Review
860‑084‑0340
Installation, Operation, Maintenance, and Testing of Contracted Systems
860‑084‑0350
Requirements after Approval of a Solar Photovoltaic Interconnection
860‑084‑0360
Volumetric Incentive Rates and Payments – Net Metering Option
860‑084‑0365
Volumetric Incentive Rate Bidding Option
860‑084‑0370
Resource Value
860‑084‑0380
Cost Recovery and Rate Impacts
860‑084‑0390
Cost Recovery Mechanism
860‑084‑0400
Data Collection
860‑084‑0420
Compliance with Pilot Program Requirements
860‑084‑0430
Data Availability
860‑084‑0440
Pilot Program Overhead
860‑084‑0450
Reports to the Legislature
Last Updated

Jun. 8, 2021

Rule 860-084-0310’s source at or​.us