OAR 141-089-0640
Pre-Construction Notification


Except as provided in OAR 141-089-0820 (Non-motorized In-stream Placer Mining in ESH – Purpose) to 141-089-0835 (Non-motorized In-stream Placer Mining in ESH - Activity-Specific Conditions):

(1)

Project Notification Required. A complete project notification must be submitted to the Department at least 30 calendar days before starting the project. A complete notification is one that contains all the information required on the form provided by the Department and all required attachments.

(2)

Review of the Notification. Within 30 calendar days of receipt, the Department will review the notification for completeness and eligibility, make one of the following determinations and notify the responsible party that:

(a)

The notification is complete and the project is eligible under the GA;

(b)

The notification is incomplete and the person must supply certain specified missing, inaccurate or insufficient information. The person may amend and resubmit the notification within 120 calendar days of the notice for reconsideration, unless instructed by the Department to do otherwise. Submission of an amended notification starts a new 30-day review period; or

(c)

The project is ineligible for certain specified reasons. The person may then either revise the project and submit for reconsideration within 120 days of the notification or apply for an individual permit under OAR 141-085. Submission of an amended notification commences a new 30-day review period.

(3)

Timeframe for Resubmittal of Incomplete or Ineligible Notifications. If a revised notification or application is not resubmitted within 120 calendar days of an incompleteness or ineligible determination, the Department will presume that the responsible party does not intend to provide revisions to the notification and may administratively close the file. If the Department closes the file under these circumstances, the Department will retain the application fee. If the Department receives a subsequent notification or application for the same or similar project after a file has been closed, the responsible party must pay any applicable fees for the new notification at time of submission.

(4)

Project Implementation. The person submitting the notification may begin the project:

(a)

Immediately upon receipt of a determination by the Department under OAR 141-089-0640 (Pre-Construction Notification)(2)(a) that the project is eligible; or

(b)

Thirty (30) calendar days after Department received the notification, unless the Department issued a determination under OAR 141-089-0640 (Pre-Construction Notification)(2)(b) or (c).

Source: Rule 141-089-0640 — Pre-Construction Notification, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=141-089-0640.

141‑089‑0620
General
141‑089‑0625
General Authorizations (GA)
141‑089‑0630
Project Applicability
141‑089‑0635
Fees
141‑089‑0640
Pre-Construction Notification
141‑089‑0645
Expiration of Project Eligibility
141‑089‑0650
General Conditions
141‑089‑0655
Enforcement
141‑089‑0656
Authorization Decision Appeals
141‑089‑0660
Minimal Disturbance Within ESH - Purpose
141‑089‑0665
Minimal Disturbance Within ESH - Eligibility Requirements
141‑089‑0670
Minimal Disturbance Within ESH - Authorized Activities
141‑089‑0675
Minimal Disturbance Within ESH - Activity-Specific Conditions
141‑089‑0680
Piling Placement And Removal Within ESH - Purpose
141‑089‑0685
Piling Placement And Removal Within ESH - Eligibility Requirements
141‑089‑0690
Piling Placement And Removal Within ESH - Authorized Activities
141‑089‑0695
Piling Placement And Removal Within ESH - Activity-Specific Conditions
141‑089‑0700
Temporary Impacts to Non-Tidal Wetlands - Purpose
141‑089‑0705
Temporary Impacts to Non-Tidal Wetlands - Eligibility Requirements
141‑089‑0710
Temporary Impacts to Non-Tidal Wetlands - Authorized Activities
141‑089‑0715
Temporary Impacts to Non-Tidal Wetlands - Activity-Specific Conditions
141‑089‑0720
Waterway Bank Stabilization - Purpose
141‑089‑0725
Waterway Bank Stabilization - Eligibility
141‑089‑0730
Waterway Bank stabilization - Authorized Activities
141‑089‑0735
Waterway Bank Stabilization - Activity-Specific Conditions
141‑089‑0740
Transportation-Related Activities - Purpose
141‑089‑0745
Transportation-Related Activities - Eligibility Requirements
141‑089‑0750
Transportation-Related Activities - Authorized Activities
141‑089‑0755
Transportation-Related Activities - Activity-Specific Conditions
141‑089‑0760
Removing Sediment Behind Tidegates - Purpose
141‑089‑0765
Removing Sediment Behind Tidegates - Eligibility Requirements-Ineligible Projects
141‑089‑0770
Removing Sediment Behind Tidegates - Mandatory Requirements
141‑089‑0775
Removing Sediment Behind Tidegates - Conditions of Issuance of General Authorization
141‑089‑0780
Waterway Habitat Restoration - Purpose
141‑089‑0785
Waterway Habitat Restoration - Eligibility Requirements
141‑089‑0790
Waterway Habitat Restoration - Authorized Activities
141‑089‑0795
Waterway Habitat Restoration - Activity-Specific Conditions
141‑089‑0800
Wetland Ecosystem Restoration - Purpose
141‑089‑0805
Wetland Ecosystem Restoration - Eligibility Requirements
141‑089‑0810
Wetland Ecosystem Restoration - Authorized Activities
141‑089‑0815
Wetland Ecosystem Restoration - Activity-Specific Conditions
141‑089‑0820
Non-motorized In-stream Placer Mining in ESH – Purpose
141‑089‑0823
Non-motorized In-stream Placer Mining within ESH - Definitions
141‑089‑0825
Non-motorized In-stream Placer Mining in ESH - Eligibility Requirements
141‑089‑0827
Non-motorized In-stream Placer Mining within ESH - Expiration and No Transfer
141‑089‑0830
Non-motorized In-stream Placer Mining in ESH - Authorized Activities
141‑089‑0835
Non-motorized In-stream Placer Mining in ESH - Activity-Specific Conditions
Last Updated

Jun. 8, 2021

Rule 141-089-0640’s source at or​.us