OAR 141-089-0650
General Conditions


The following conditions apply to all general authorizations, unless otherwise specified in a specific GA or an authorization issued under a GA:

(1)

Responsible Party. The person listed on the notification as the responsible party is responsible for the activities of all contractors or other operators involved in project work covered by the GA.

(2)

Copy of Approved Notification Available for Inspection. A copy of the notification approved by the Department must be available at the work site whenever noticed activities are being conducted.

(3)

Site Access Required. Employees of the Department and all authorized representatives must be permitted access to the project area at all reasonable times for the purpose of inspecting work performed under a notification.

(4)

Archeological Resources. If any archeological sites, resources or artifacts are discovered during construction, work must immediately cease and the State Historic Preservation Office must be contacted.

(5)

ODFW Fish Passage Requirement. The activity must meet Oregon Department of Fish and Wildlife requirements for fish passage before the project is started (ORS 509.580 (Definitions for ORS 509.580 to 509.590, 509.600 to 509.645 and 509.910) through 509.901 and OAR 635-412-0005 (Definitions) through 635-412-0040 (Mitigation Criteria)).

(6)

Hazards to Recreation, Navigation and Fishing. The activity must be timed so as not to interfere with or create a hazard to recreational and commercial navigation and fishing.

(7)

Work Period in Jurisdictional Areas. Fill or removal activities below the Ordinary High Water Line must be conducted when recommended by ODFW, unless otherwise coordinated with Oregon Department of Fish and Wildlife and approved in writing by DSL. Work is prohibited when fish eggs are present within the reach where activities are being conducted.

(8)

Pre-Construction Resource Area Fencing or Flagging. Prior to any site grading, the boundaries of any avoided wetlands, waterways and riparian areas adjacent to the project site must be surrounded by noticeable construction fencing or flagging. There must be no vegetation removal or heavy equipment within marked areas. The marked areas must be maintained during construction of the project and be removed immediately upon project completion.

(9)

Erosion Control Methods. The following erosion control measures must be installed at the construction site prior to construction and maintained during and after construction to prevent erosion and minimize movement of soil into waters of this state:

(a)

All exposed soils must be stabilized during and after construction in order to prevent erosion and sedimentation;

(b)

Filter bags, sediment fences, sediment traps or catch basins, leave strips or berms, or other measures must be used to prevent movement of soil into waterways and wetlands;

(c)

To prevent erosion, use of compost berms, impervious materials or other equally effective methods, must be used to protect soil stockpiled during rain events or when the stockpile site is not moved or reshaped for more than 48 hours;

(d)

Unless part of the permanent fill, all construction access points through, and staging areas in, riparian and wetland areas must use removable pads or mats to prevent soil compaction. However, in some wetland areas under dry summer conditions, this requirement may be waived upon approval by DSL. At project completion, disturbed areas with soil exposed by construction activities must be stabilized by mulching and native vegetative plantings/seeding. Sterile grass may be used instead of native vegetation for temporary sediment control if native vegetation is unavailable. If soils are to remain exposed for more than seven days after completion of the permitted work, they must be covered with erosion control pads, mats or similar erosion control devices until vegetative stabilization is installed;

(e)

Where vegetation is used for erosion control on slopes steeper than 2:1, tackified seed mulch must be used so the seed does not wash away before germination and rooting;

(f)

Dredged or other excavated material must be placed on upland areas having stable slopes and must be prevented from eroding back into waterways and wetlands;

(g)

Erosion control measures must be inspected and maintained as necessary to ensure their continued effectiveness until soils become stabilized; and

(h)

All erosion control structures must be removed when the project is complete and soils are stabilized and vegetated.

(10)

Hazardous, Toxic, and Waste Material Handling. Petroleum products, chemicals, fresh cement, sandblasted material and chipped paint, wood treated with leachable preservatives or other deleterious waste materials must not be allowed to enter waters of this state. Machinery refueling is to occur at least 150 feet from waters of this state and confined in a designated area to prevent spillage into waters of this state. Barges must have a containment system to effectively prevent petroleum products or other deleterious material from entering waters of this state. Project-related spills into waters of this state or onto land with a potential to enter waters of this state must be reported to the Oregon Emergency Response System (OERS) at 1-800-452-0311.

(11)

Raising or Redirecting Water. The project must not cause water to rise or be redirected and result in damage to structures or property.

(12)

Waste Disposal. Old piling and other waste material discarded by the project must be disposed of in an appropriate disposal facility. There must be no temporary storage of piling or other waste material below top of bank, in any wetland, Federal Emergency Management Administration designated floodway, or an area historically subject to landslides.

(13)

DSL May Halt or Modify. DSL retains the authority to temporarily halt or modify the project in case of unforeseen damage to natural resources.

(14)

Work Area Isolation. The work area must be isolated from the water during construction. All structures and materials used to isolate the work area must be removed immediately following construction and water flow returned to pre-construction conditions. All fish must be salvaged from the isolated area in accordance with Oregon Department of Fish and Wildlife requirements.

(15)

Spoil Disposal. Spoil materials, not used in the project, must be placed in an upland location. Spoil materials used in the project must be included in the cumulative removal-fill calculation for the activity.
141‑089‑0620
General
141‑089‑0625
General Authorizations (GA)
141‑089‑0630
Project Applicability
141‑089‑0635
Fees
141‑089‑0640
Pre-Construction Notification
141‑089‑0645
Expiration of Project Eligibility
141‑089‑0650
General Conditions
141‑089‑0655
Enforcement
141‑089‑0656
Authorization Decision Appeals
141‑089‑0660
Minimal Disturbance Within ESH - Purpose
141‑089‑0665
Minimal Disturbance Within ESH - Eligibility Requirements
141‑089‑0670
Minimal Disturbance Within ESH - Authorized Activities
141‑089‑0675
Minimal Disturbance Within ESH - Activity-Specific Conditions
141‑089‑0680
Piling Placement And Removal Within ESH - Purpose
141‑089‑0685
Piling Placement And Removal Within ESH - Eligibility Requirements
141‑089‑0690
Piling Placement And Removal Within ESH - Authorized Activities
141‑089‑0695
Piling Placement And Removal Within ESH - Activity-Specific Conditions
141‑089‑0700
Temporary Impacts to Non-Tidal Wetlands - Purpose
141‑089‑0705
Temporary Impacts to Non-Tidal Wetlands - Eligibility Requirements
141‑089‑0710
Temporary Impacts to Non-Tidal Wetlands - Authorized Activities
141‑089‑0715
Temporary Impacts to Non-Tidal Wetlands - Activity-Specific Conditions
141‑089‑0720
Waterway Bank Stabilization - Purpose
141‑089‑0725
Waterway Bank Stabilization - Eligibility
141‑089‑0730
Waterway Bank stabilization - Authorized Activities
141‑089‑0735
Waterway Bank Stabilization - Activity-Specific Conditions
141‑089‑0740
Transportation-Related Activities - Purpose
141‑089‑0745
Transportation-Related Activities - Eligibility Requirements
141‑089‑0750
Transportation-Related Activities - Authorized Activities
141‑089‑0755
Transportation-Related Activities - Activity-Specific Conditions
141‑089‑0760
Removing Sediment Behind Tidegates - Purpose
141‑089‑0765
Removing Sediment Behind Tidegates - Eligibility Requirements-Ineligible Projects
141‑089‑0770
Removing Sediment Behind Tidegates - Mandatory Requirements
141‑089‑0775
Removing Sediment Behind Tidegates - Conditions of Issuance of General Authorization
141‑089‑0780
Waterway Habitat Restoration - Purpose
141‑089‑0785
Waterway Habitat Restoration - Eligibility Requirements
141‑089‑0790
Waterway Habitat Restoration - Authorized Activities
141‑089‑0795
Waterway Habitat Restoration - Activity-Specific Conditions
141‑089‑0800
Wetland Ecosystem Restoration - Purpose
141‑089‑0805
Wetland Ecosystem Restoration - Eligibility Requirements
141‑089‑0810
Wetland Ecosystem Restoration - Authorized Activities
141‑089‑0815
Wetland Ecosystem Restoration - Activity-Specific Conditions
141‑089‑0820
Non-motorized In-stream Placer Mining in ESH – Purpose
141‑089‑0823
Non-motorized In-stream Placer Mining within ESH - Definitions
141‑089‑0825
Non-motorized In-stream Placer Mining in ESH - Eligibility Requirements
141‑089‑0827
Non-motorized In-stream Placer Mining within ESH - Expiration and No Transfer
141‑089‑0830
Non-motorized In-stream Placer Mining in ESH - Authorized Activities
141‑089‑0835
Non-motorized In-stream Placer Mining in ESH - Activity-Specific Conditions
Last Updated

Jun. 8, 2021

Rule 141-089-0650’s source at or​.us