OAR 141-089-0730
Waterway Bank stabilization - Authorized Activities


(1)

Bio-Engineering. This activity includes placement of woody vegetation, vegetated geogrids, biodegradable logs, straw bales or straw logs used for bank protection, bank reshaping, terracing and erosion control.

(2)

Bank Terracing. This activity includes bank terracing and sloping to facilitate establishment of woody vegetation. The project must meet the following criteria:

(a)

The slope must not be steeper than 3:1 (H/V) ratio;

(b)

Bank treatments must be replanted with native woody vegetation; and

(c)

If fabric is necessary, no petroleum-based fabric is allowed.

(3)

Placement of Large Wood. Trees or root wads may be used. The project must meet the following criteria:

(a)

Trees must have a trunk diameter greater than or equal to 12 inches;

(b)

The basal ends must be oriented upstream;

(c)

If fastening is necessary, only smooth, single-string wire, degradable rope or pinning may be used. Braided wire cable is not allowed; and

(d)

If anchoring is necessary, only rock ballast, untreated wood posts, stabilizing wood or key pieces of wood may be used as anchors.

(4)

Engineered Log Jams. Log jams may be placed in order to stabilize the bank for woody vegetation establishment. The project must meet the following criteria:

(a)

The length of key pieces of wood with trimmed rootwads must be one and one-half times the bankfull width or a minimum of 25 feet in length when bankfull width exceeds 15 feet. The length of key pieces of wood with trimmed rootwads must be the twice the bankfull width or a minimum of 30 feet in length when bankfull width exceeds 15 feet;

(b)

Large wood must be intact, hard and undecayed to partially decayed hardwoods or conifers;

(c)

The log jam must not occupy more than 20 percent of the bankfull width;

(d)

If fastening is necessary, only smooth, single-string wire, pinning or degradable rope may be used. Braided wire cable is not allowed; and

(e)

If anchoring is necessary, only rock ballast, untreated posts, stabilizing wood or key pieces of wood may be used as anchors.

(5)

Log Toe Placement. The project must meet the following criteria:

(a)

Log toes must not extend more than one foot above the elevation of the water at base flow; and

(b)

Logs must be large enough to withstand the hydraulic energy in the stream and be anchored securely to the bank by burial.

(6)

Porous Weir. This activity includes the construction of a self-sustaining, low profile, structure including but not limited to cross vanes and artificial riffles. A porous weir delays but does not store water. It is used to redirect flow toward the center of the channel, provide energy dissipation and promote increased sedimentation along banks while allowing fish passage through a porous design. The project must meet the following criteria:

(a)

Porous weirs must be placed so scour pools occur in areas where pools would naturally form in a pool and riffle complex;

(b)

Porous weirs must not result in culvert inlet or outlet scour;

(c)

Porous weirs must be sized appropriately for the system so as not to require annual maintenance;

(d)

Porous weirs must be constructed of materials that mimic natural substrate found within the system;

(e)

The structure must not exceed 100 cubic yards and 40% of the channel cross-section width; and

(f)

The activity is limited to 100 cubic yards for every one-half mile of waterway, unless otherwise approved by the Department.

Source: Rule 141-089-0730 — Waterway Bank stabilization - Authorized Activities, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=141-089-0730.

141‑089‑0620
General
141‑089‑0625
General Authorizations (GA)
141‑089‑0630
Project Applicability
141‑089‑0635
Fees
141‑089‑0640
Pre-Construction Notification
141‑089‑0645
Expiration of Project Eligibility
141‑089‑0650
General Conditions
141‑089‑0655
Enforcement
141‑089‑0656
Authorization Decision Appeals
141‑089‑0660
Minimal Disturbance Within ESH - Purpose
141‑089‑0665
Minimal Disturbance Within ESH - Eligibility Requirements
141‑089‑0670
Minimal Disturbance Within ESH - Authorized Activities
141‑089‑0675
Minimal Disturbance Within ESH - Activity-Specific Conditions
141‑089‑0680
Piling Placement And Removal Within ESH - Purpose
141‑089‑0685
Piling Placement And Removal Within ESH - Eligibility Requirements
141‑089‑0690
Piling Placement And Removal Within ESH - Authorized Activities
141‑089‑0695
Piling Placement And Removal Within ESH - Activity-Specific Conditions
141‑089‑0700
Temporary Impacts to Non-Tidal Wetlands - Purpose
141‑089‑0705
Temporary Impacts to Non-Tidal Wetlands - Eligibility Requirements
141‑089‑0710
Temporary Impacts to Non-Tidal Wetlands - Authorized Activities
141‑089‑0715
Temporary Impacts to Non-Tidal Wetlands - Activity-Specific Conditions
141‑089‑0720
Waterway Bank Stabilization - Purpose
141‑089‑0725
Waterway Bank Stabilization - Eligibility
141‑089‑0730
Waterway Bank stabilization - Authorized Activities
141‑089‑0735
Waterway Bank Stabilization - Activity-Specific Conditions
141‑089‑0740
Transportation-Related Activities - Purpose
141‑089‑0745
Transportation-Related Activities - Eligibility Requirements
141‑089‑0750
Transportation-Related Activities - Authorized Activities
141‑089‑0755
Transportation-Related Activities - Activity-Specific Conditions
141‑089‑0760
Removing Sediment Behind Tidegates - Purpose
141‑089‑0765
Removing Sediment Behind Tidegates - Eligibility Requirements-Ineligible Projects
141‑089‑0770
Removing Sediment Behind Tidegates - Mandatory Requirements
141‑089‑0775
Removing Sediment Behind Tidegates - Conditions of Issuance of General Authorization
141‑089‑0780
Waterway Habitat Restoration - Purpose
141‑089‑0785
Waterway Habitat Restoration - Eligibility Requirements
141‑089‑0790
Waterway Habitat Restoration - Authorized Activities
141‑089‑0795
Waterway Habitat Restoration - Activity-Specific Conditions
141‑089‑0800
Wetland Ecosystem Restoration - Purpose
141‑089‑0805
Wetland Ecosystem Restoration - Eligibility Requirements
141‑089‑0810
Wetland Ecosystem Restoration - Authorized Activities
141‑089‑0815
Wetland Ecosystem Restoration - Activity-Specific Conditions
141‑089‑0820
Non-motorized In-stream Placer Mining in ESH – Purpose
141‑089‑0823
Non-motorized In-stream Placer Mining within ESH - Definitions
141‑089‑0825
Non-motorized In-stream Placer Mining in ESH - Eligibility Requirements
141‑089‑0827
Non-motorized In-stream Placer Mining within ESH - Expiration and No Transfer
141‑089‑0830
Non-motorized In-stream Placer Mining in ESH - Authorized Activities
141‑089‑0835
Non-motorized In-stream Placer Mining in ESH - Activity-Specific Conditions
Last Updated

Jun. 8, 2021

Rule 141-089-0730’s source at or​.us