OAR 141-089-0790
Waterway Habitat Restoration - Authorized Activities


The following activities may be combined for a single project and the volume thresholds for each activity may be calculated separately:

(1)

Barrier Removal. Barriers may be removed to reconnect waterway corridors, reestablish wetlands, restore natural channel and flow conditions, and assist fish and wildlife movement. The project must meet the following criteria:

(a)

Removal is limited to artificially created barriers including, but not limited to culverts, dams, earthen embankments, spillway systems, tidegates, outfalls and pipes; and

(b)

Cumulative removal-fill volume for this activity must not exceed 200 cubic yards.

(2)

Grade Control. This activity includes construction of grade control structures to stabilize channel grade, reduce erosion, reconnect a waterway to the floodplain or reduce channel incision. The project must meet the following criteria:

(a)

Grade control structures must be constructed of materials that mimic natural substrate found within the system;

(b)

Grade control structures must be sized appropriately for the system to prevent creating a fish passage barrier or require annual maintenance; and

(c)

The activity is limited to 100 cubic yards for every one-half mile of waterway, unless otherwise approved by the Department.

(3)

Fish and Wildlife Passage. This activity includes installation or replacement of fish passage structures including, but not limited to vertical slot fishways, nature-like fishways and lamprey ramps to aid fish and/or wildlife passage. The project must meet the following criteria:

(a)

Oregon Department of Fish and Wildlife (ODFW) must be notified;

(b)

Passage structures must be designed to consider the velocity, depth, pool-length and jump-height preferences of native species;

(c)

Passage structures must be sized appropriately for the system yet be stable; and

(d)

The activity is limited to 100 cubic yards for every one-half mile of waterway, unless otherwise approved by the Department.

(4)

Installation or Replacement of Fish Screening Structures. The project must meet the following criteria:

(a)

Oregon Department of Fish and Wildlife (ODFW) must be notified;

(b)

Screens must meet ODFW fish screen criteria; and

(c)

Cumulative removal-fill for this activity must not exceed 100 cubic yards in waters of this state.

(5)

Porous Weir. This activity includes the construction of a self-sustaining, low profile, structure. A porous weir delays but does not store water. It is used to redirect flow toward the center of the channel, provide energy dissipation and promote increased sedimentation along banks while allowing fish passage through a porous design. This activity includes, but is not limited to cross vanes and artificial riffles. The project must meet the following criteria:

(a)

Porous weirs must be placed so scour pools occur in areas where pools would naturally form in a pool and riffle complex;

(b)

Porous weirs must not result in culvert inlet or outlet scour;

(c)

Porous weirs must be sized appropriately for the system so as not to require annual maintenance;

(d)

Porous weirs must be constructed of materials that mimic natural substrate found within the system;

(e)

The structure must not exceed 100 cubic yards and 40% of the channel cross-section width; and

(f)

The activity is limited to 100 cubic yards for every one-half mile of waterway, unless otherwise approved by the Department.

(6)

Side Channel and Alcove Habitat. This activity is limited to reconnecting existing side channel or alcove habitat, as follows:

(a)

Cumulative removal-fill volume may not exceed 200 cubic yards unless otherwise approved by the Department;

(b)

Reconnection consists only of the removal of artificial barriers; and

(c)

The side channel or alcove being reconnected must be naturally formed and does not require alteration or reconstruction.

(7)

Remove or Replace Existing Culverts and Tide Gates for Fish Passage. Tide gate and culvert replacement for fish passage through the installation of a larger culvert or for replacing the culvert with a bridge is allowed when:

(a)

The new culvert or tidegate is not exempt ; and

(b)

The project is consistent with ODFW Fish Passage Statutes, as evidenced in writing by an ODFW fisheries biologist.

Source: Rule 141-089-0790 — Waterway Habitat Restoration - Authorized Activities, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=141-089-0790.

141‑089‑0620
General
141‑089‑0625
General Authorizations (GA)
141‑089‑0630
Project Applicability
141‑089‑0635
Fees
141‑089‑0640
Pre-Construction Notification
141‑089‑0645
Expiration of Project Eligibility
141‑089‑0650
General Conditions
141‑089‑0655
Enforcement
141‑089‑0656
Authorization Decision Appeals
141‑089‑0660
Minimal Disturbance Within ESH - Purpose
141‑089‑0665
Minimal Disturbance Within ESH - Eligibility Requirements
141‑089‑0670
Minimal Disturbance Within ESH - Authorized Activities
141‑089‑0675
Minimal Disturbance Within ESH - Activity-Specific Conditions
141‑089‑0680
Piling Placement And Removal Within ESH - Purpose
141‑089‑0685
Piling Placement And Removal Within ESH - Eligibility Requirements
141‑089‑0690
Piling Placement And Removal Within ESH - Authorized Activities
141‑089‑0695
Piling Placement And Removal Within ESH - Activity-Specific Conditions
141‑089‑0700
Temporary Impacts to Non-Tidal Wetlands - Purpose
141‑089‑0705
Temporary Impacts to Non-Tidal Wetlands - Eligibility Requirements
141‑089‑0710
Temporary Impacts to Non-Tidal Wetlands - Authorized Activities
141‑089‑0715
Temporary Impacts to Non-Tidal Wetlands - Activity-Specific Conditions
141‑089‑0720
Waterway Bank Stabilization - Purpose
141‑089‑0725
Waterway Bank Stabilization - Eligibility
141‑089‑0730
Waterway Bank stabilization - Authorized Activities
141‑089‑0735
Waterway Bank Stabilization - Activity-Specific Conditions
141‑089‑0740
Transportation-Related Activities - Purpose
141‑089‑0745
Transportation-Related Activities - Eligibility Requirements
141‑089‑0750
Transportation-Related Activities - Authorized Activities
141‑089‑0755
Transportation-Related Activities - Activity-Specific Conditions
141‑089‑0760
Removing Sediment Behind Tidegates - Purpose
141‑089‑0765
Removing Sediment Behind Tidegates - Eligibility Requirements-Ineligible Projects
141‑089‑0770
Removing Sediment Behind Tidegates - Mandatory Requirements
141‑089‑0775
Removing Sediment Behind Tidegates - Conditions of Issuance of General Authorization
141‑089‑0780
Waterway Habitat Restoration - Purpose
141‑089‑0785
Waterway Habitat Restoration - Eligibility Requirements
141‑089‑0790
Waterway Habitat Restoration - Authorized Activities
141‑089‑0795
Waterway Habitat Restoration - Activity-Specific Conditions
141‑089‑0800
Wetland Ecosystem Restoration - Purpose
141‑089‑0805
Wetland Ecosystem Restoration - Eligibility Requirements
141‑089‑0810
Wetland Ecosystem Restoration - Authorized Activities
141‑089‑0815
Wetland Ecosystem Restoration - Activity-Specific Conditions
141‑089‑0820
Non-motorized In-stream Placer Mining in ESH – Purpose
141‑089‑0823
Non-motorized In-stream Placer Mining within ESH - Definitions
141‑089‑0825
Non-motorized In-stream Placer Mining in ESH - Eligibility Requirements
141‑089‑0827
Non-motorized In-stream Placer Mining within ESH - Expiration and No Transfer
141‑089‑0830
Non-motorized In-stream Placer Mining in ESH - Authorized Activities
141‑089‑0835
Non-motorized In-stream Placer Mining in ESH - Activity-Specific Conditions
Last Updated

Jun. 8, 2021

Rule 141-089-0790’s source at or​.us