OAR 345-027-0220
Request for Approval


(1)

Before submitting a request for approval to construct, operate and retire a gas storage testing pipeline, the certificate holder must:

(a)

Inform the Department of the proposed pipeline, including its diameter, length, location, capacity and maximum operating pressure; and

(b)

Provide to the Department a map showing the location of the proposed pipeline.

(2)

After receiving the information described in section (1) of this rule, the Department must confer with the certificate holder about the Council substantive standards and information requirements that might apply to the proposed pipeline and any extraordinary circumstances that might affect the time requirements for completing the approval process. Within 7 days after conferring with the certificate holder, the Department must send a letter to the certificate holder that includes the following:

(a)

Identification of the Council substantive standards that are applicable to the request for approval of the proposed pipeline;

(b)

Identification of the information requirements that are applicable to the request for approval of the proposed pipeline;

(c)

The time requirements for the approval process, if different from the time requirements described in OAR 345-027-0530.

(3)

The certificate holder must submit to the Department a written request for approval to construct, operate and retire a gas storage testing pipeline with the fee required by the fee schedule established under ORS 469.441 (Justification of fees charged). The certificate holder must submit two printed copies of the request, and an electronic version of the full request in a non-copy-protected electronic format acceptable to the Department. The certificate holder must provide additional printed copies to the Department upon request and copies or access to copies to any person requesting copies.

(4)

In a request for approval, the certificate holder must include:

(a)

The name and mailing address of the certificate holder and the name, mailing address, email address and phone number of the individual responsible for submitting the request;

(b)

A description of the purpose and operation of the proposed pipeline and a discussion of whether the use of the gas storage testing pipeline for reservoir testing or maintenance will require an increase in the compression available in the Council certified facility to which the proposed pipeline would connect in addition to the compression that is permitted under the site certificate;

(c)

Identification of the Council certified facility to which the proposed pipeline would connect;

(d)

A description of the proposed pipeline, including its diameter, length, location, capacity and maximum operating pressure;

(e)

A map showing the location of the proposed pipeline;

(f)

A list of the names and mailing addresses of all owners of record, as shown on the most recent property tax assessment role, of property where the proposed pipeline is located and within 500 feet of that property;

(g)

The information that the Department has identified in the letter described in section (2) of this rule; and

(h)

Any other information that the Department requests as needed to make the findings described in the applicable standards.

Source: Rule 345-027-0220 — Request for Approval, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=345-027-0220.

345‑027‑0110
Termination of a Site Certificate
345‑027‑0210
General
345‑027‑0220
Request for Approval
345‑027‑0230
Review of a Request for Approval
345‑027‑0240
Conditions
345‑027‑0311
Applicability
345‑027‑0313
Certificate Expiration
345‑027‑0350
Changes Requiring an Amendment
345‑027‑0351
Review Processes for Requests for Amendment
345‑027‑0353
Changes Exempt from Requiring an Amendment
345‑027‑0355
Written Evaluations for Changes Not Requiring Amendment
345‑027‑0357
Amendment Determination Request
345‑027‑0359
Pre-Amendment Conference
345‑027‑0360
Preliminary Request for Amendment
345‑027‑0363
Determination of Completeness for a Request for Amendment
345‑027‑0365
Draft Proposed Order for a Request for Amendment
345‑027‑0367
Public Comment and Hearing on the Draft Proposed Order for Requests for Amendment Under Type A Review
345‑027‑0368
Public Written Comment on the Draft Proposed Order for Requests for Amendment Under Type B Review
345‑027‑0371
Proposed Order, Requests for Contested Case and Council’s Final Decision on Requests for Amendment Under Type A Review
345‑027‑0372
Proposed Order and Council’s Final Decision on Requests for Amendment Under Type B Review
345‑027‑0375
Scope of Council’s Review
345‑027‑0380
Type C Review Process for Pre-Operational Requests for Amendment
345‑027‑0385
Request for Amendment to Extend Construction Deadlines
345‑027‑0390
Request by Any Person for Amendment to Apply Later-Adopted Laws
345‑027‑0400
Request for Amendment to Transfer Ownership, Possession or Control of the Facility or the Certificate Holder
Last Updated

Jun. 8, 2021

Rule 345-027-0220’s source at or​.us