OAR 345-027-0350
Changes Requiring an Amendment


Except for changes allowed under OAR 345-027-0353 (Changes Exempt from Requiring an Amendment), an amendment to a site certificate is required to:

(1)

Transfer ownership of the facility or the certificate holder as described in OAR 345-027-0400 (Request for Amendment to Transfer Ownership, Possession or Control of the Facility or the Certificate Holder);

(2)

Apply later-adopted laws as described in OAR 345-027-0390 (Request by Any Person for Amendment to Apply Later-Adopted Laws);

(3)

Extend the construction beginning or completion deadline as described in OAR 345-027-0385 (Request for Amendment to Extend Construction Deadlines);

(4)

Design, construct, or operate a facility in a manner different from the description in the site certificate, if the proposed change:

(a)

Could result in a significant adverse impact that the Council has not addressed in an earlier order and the impact affects a resource or interest protected by an applicable law or Council standard;

(b)

Could impair the certificate holder’s ability to comply with a site certificate condition; or

(c)

Could require a new condition or a change to a condition in the site certificate.

Source: Rule 345-027-0350 — Changes Requiring an Amendment, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=345-027-0350.

345–027–0110
Termination of a Site Certificate
345–027–0210
General
345–027–0220
Request for Approval
345–027–0230
Review of a Request for Approval
345–027–0240
Conditions
345–027–0311
Applicability
345–027–0313
Certificate Expiration
345–027–0350
Changes Requiring an Amendment
345–027–0351
Review Processes for Requests for Amendment
345–027–0353
Changes Exempt from Requiring an Amendment
345–027–0355
Written Evaluations for Changes Not Requiring Amendment
345–027–0357
Amendment Determination Request
345–027–0359
Pre-Amendment Conference
345–027–0360
Preliminary Request for Amendment
345–027–0363
Determination of Completeness for a Request for Amendment
345–027–0365
Draft Proposed Order for a Request for Amendment
345–027–0367
Public Comment and Hearing on the Draft Proposed Order for Requests for Amendment Under Type A Review
345–027–0368
Public Written Comment on the Draft Proposed Order for Requests for Amendment Under Type B Review
345–027–0371
Proposed Order, Requests for Contested Case and Council’s Final Decision on Requests for Amendment Under Type A Review
345–027–0372
Proposed Order and Council’s Final Decision on Requests for Amendment Under Type B Review
345–027–0375
Scope of Council’s Review
345–027–0380
Type C Review Process for Pre-Operational Requests for Amendment
345–027–0385
Request for Amendment to Extend Construction Deadlines
345–027–0390
Request by Any Person for Amendment to Apply Later-Adopted Laws
345–027–0400
Request for Amendment to Transfer Ownership, Possession or Control of the Facility or the Certificate Holder
Last Updated

Jun. 8, 2021

Rule 345-027-0350’s source at or​.us