OAR 345-027-0210
General


(1)

A person may not construct a gas storage testing pipeline unless the certificate holder of the Council certified facility to which the pipeline would connect obtains, before construction, the approval of the Department for the construction, operation and retirement of the proposed pipeline as required under ORS 469.405 (Amendment of site certificate)(3).

(2)

For the purposes of OAR 345-027-0510 through 345-027-0540:

(a)

“Gas storage testing pipeline” means a pipeline, but not a temporary pipeline, that is less than 16 inches in diameter and less than five miles in length, that is used to test or maintain an underground gas storage reservoir, and that would connect to a Council certified facility if the storage reservoir proves feasible for operational use;

(b)

“Temporary pipeline” means a pipeline that has no potential for operational use;

(c)

“Council certified facility” means an energy facility for which the Council has issued a site certificate that is either a surface facility related to an underground gas storage reservoir or a gas pipeline;

(d)

“Connect” means join for the purpose of operational use;

(e)

“Test or maintain” means transporting gas to an underground gas storage reservoir for the purposes of determining whether the reservoir is feasible for operational use or maintaining the gas storage capacity of the reservoir but does not include operational use;

(f)

“Operational use” means transporting gas to an underground gas storage reservoir for the purpose of storing gas until it is needed for sale or for withdrawing gas from an underground gas storage reservoir for the purpose of sale;

(g)

“Council substantive standards” means the following standards:

(A)

Structural Standard, OAR 345-022-0020 (Structural Standard);

(B)

Soil Protection, OAR 345-022-0022 (Soil Protection);

(C)

Protected Areas, OAR 345-022-0040 (Protected Areas)(1) but excluding (2) and (3);

(D)

Retirement and Financial Assurance, OAR 345-022-0050 (Retirement and Financial Assurance);

(E)

Fish and Wildlife Habitat, OAR 345-022-0060 (Fish and Wildlife Habitat);

(F)

Threatened and Endangered Species, OAR 345-022-0070 (Threatened and Endangered Species)

(G)

Scenic Resources, OAR 345-022-0080 (Scenic Resources);

(H)

Historic, Cultural and Archaeological Resources, OAR 345-022-0090 (Historic, Cultural and Archaeological Resources);

(I)

Recreation, OAR 345-022-0100 (Recreation);

(J)

Public Services, OAR 345-022-0110 (Public Services);

(K)

Waste Minimization, OAR 345-022-0120 (Waste Minimization); and

(L)

Public Health and Safety, OAR 345-024-0030 (Public Health and Safety Standards for Surface Facilities Related to Underground Gas Storage Reservoirs)(2), (3) and (4);

(h)

“Information requirements” means information that would support the findings described in OAR 345-024-0030 (Public Health and Safety Standards for Surface Facilities Related to Underground Gas Storage Reservoirs)(2) and the information described in OAR 345-021-0010 (Contents of an Application)(1)(h), (i), (j), (L), (m), (p), (q), (r), (s), (t), (u), (v) and (w).
345‑027‑0110
Termination of a Site Certificate
345‑027‑0210
General
345‑027‑0220
Request for Approval
345‑027‑0230
Review of a Request for Approval
345‑027‑0240
Conditions
345‑027‑0311
Applicability
345‑027‑0313
Certificate Expiration
345‑027‑0350
Changes Requiring an Amendment
345‑027‑0351
Review Processes for Requests for Amendment
345‑027‑0353
Changes Exempt from Requiring an Amendment
345‑027‑0355
Written Evaluations for Changes Not Requiring Amendment
345‑027‑0357
Amendment Determination Request
345‑027‑0359
Pre-Amendment Conference
345‑027‑0360
Preliminary Request for Amendment
345‑027‑0363
Determination of Completeness for a Request for Amendment
345‑027‑0365
Draft Proposed Order for a Request for Amendment
345‑027‑0367
Public Comment and Hearing on the Draft Proposed Order for Requests for Amendment Under Type A Review
345‑027‑0368
Public Written Comment on the Draft Proposed Order for Requests for Amendment Under Type B Review
345‑027‑0371
Proposed Order, Requests for Contested Case and Council’s Final Decision on Requests for Amendment Under Type A Review
345‑027‑0372
Proposed Order and Council’s Final Decision on Requests for Amendment Under Type B Review
345‑027‑0375
Scope of Council’s Review
345‑027‑0380
Type C Review Process for Pre-Operational Requests for Amendment
345‑027‑0385
Request for Amendment to Extend Construction Deadlines
345‑027‑0390
Request by Any Person for Amendment to Apply Later-Adopted Laws
345‑027‑0400
Request for Amendment to Transfer Ownership, Possession or Control of the Facility or the Certificate Holder