OAR 345-027-0355
Written Evaluations for Changes Not Requiring Amendment


(1)

For a proposed change that would add area to the site boundary, see OAR 345-027-0357 (Amendment Determination Request)(1). For a proposed change to the facility that does not include adding area to the site boundary, the certificate holder may evaluate OAR 345-027-0350 (Changes Requiring an Amendment) and 345-027-0353 (Changes Exempt from Requiring an Amendment) and conclude that the proposed change does not require an amendment. If the certificate holder concludes that a proposed change to the facility does not require an amendment to the site certificate, the certificate holder must complete a written evaluation if the change:

(a)

Could be included in and governed by the site certificate, but the certificate holder has concluded the change is not described in OAR 345-027-0350 (Changes Requiring an Amendment); or

(b)

Is exempt from requiring an amendment under OAR 345-027-0353 (Changes Exempt from Requiring an Amendment).

(2)

The written evaluation must explain why an amendment is not required, must be completed before implementing any change, and must be included in the next semiannual construction progress report or the Facility Modification Report required under OAR 345-026-0080 (Reporting Requirements for Energy Facilities). The written evaluation must be retained for the life of the facility.

(3)

The Department may, at any time, inspect the changes made to the facility and may inspect the certificate holder’s written evaluation concluding that the change did not require an amendment.
(4) When the certificate holder implements a change without an amendment, the Department may initiate an enforcement action as described in Division 29 if the Department determines the change required an amendment to the site certificate.

Source: Rule 345-027-0355 — Written Evaluations for Changes Not Requiring Amendment, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=345-027-0355.

345–027–0110
Termination of a Site Certificate
345–027–0210
General
345–027–0220
Request for Approval
345–027–0230
Review of a Request for Approval
345–027–0240
Conditions
345–027–0311
Applicability
345–027–0313
Certificate Expiration
345–027–0350
Changes Requiring an Amendment
345–027–0351
Review Processes for Requests for Amendment
345–027–0353
Changes Exempt from Requiring an Amendment
345–027–0355
Written Evaluations for Changes Not Requiring Amendment
345–027–0357
Amendment Determination Request
345–027–0359
Pre-Amendment Conference
345–027–0360
Preliminary Request for Amendment
345–027–0363
Determination of Completeness for a Request for Amendment
345–027–0365
Draft Proposed Order for a Request for Amendment
345–027–0367
Public Comment and Hearing on the Draft Proposed Order for Requests for Amendment Under Type A Review
345–027–0368
Public Written Comment on the Draft Proposed Order for Requests for Amendment Under Type B Review
345–027–0371
Proposed Order, Requests for Contested Case and Council’s Final Decision on Requests for Amendment Under Type A Review
345–027–0372
Proposed Order and Council’s Final Decision on Requests for Amendment Under Type B Review
345–027–0375
Scope of Council’s Review
345–027–0380
Type C Review Process for Pre-Operational Requests for Amendment
345–027–0385
Request for Amendment to Extend Construction Deadlines
345–027–0390
Request by Any Person for Amendment to Apply Later-Adopted Laws
345–027–0400
Request for Amendment to Transfer Ownership, Possession or Control of the Facility or the Certificate Holder
Last Updated

Jun. 8, 2021

Rule 345-027-0355’s source at or​.us