OAR 345-027-0353
Changes Exempt from Requiring an Amendment


An amendment to a site certificate is not required for a proposed change in the design, construction or operation of a facility that is in substantial compliance with the terms and conditions of the site certificate, and is a change:

(1)

To an electrical generation facility that would increase the electrical generating capacity and would not increase the number of electric generators at the site, change fuel type, increase fuel consumption by more than 10 percent or enlarge the facility site;

(2)

To the number or location of pipelines for a surface facility related to an underground gas storage reservoir that would not result in the facility exceeding permitted daily throughput or a change to the site boundary;

(3)

To the number, size, or location of pipelines for a geothermal energy facility that would not result in a change to the site boundary;

(4)

To a pipeline that is a related or supporting facility that delivers natural gas to the energy facility, if the change would extend or modify the pipeline or expand the right-of-way, when the change is exclusively to serve gas users other than the energy facility;

(5)

To a transmission line that is a related or supporting facility, if the change would extend or modify the transmission line or expand the right-of-way, when the change is exclusively to serve the transmission needs of a separate energy facility or energy user; or

(6)

To construct a pipeline less than 16 inches in diameter and less than five miles in length to test or maintain an underground gas storage reservoir. If the proposed pipeline would connect to a surface facility related to an underground gas storage reservoir for which the Council has issued a site certificate or to a gas pipeline for which the Council has issued a site certificate, the certificate holder must obtain, prior to construction, the approval of the Department for the construction, operation and retirement of the proposed pipeline. To obtain Department approval, the certificate holder must submit a request as described in OAR 345-027-0510 through 345-027-0540.

Source: Rule 345-027-0353 — Changes Exempt from Requiring an Amendment, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=345-027-0353.

345–027–0110
Termination of a Site Certificate
345–027–0210
General
345–027–0220
Request for Approval
345–027–0230
Review of a Request for Approval
345–027–0240
Conditions
345–027–0311
Applicability
345–027–0313
Certificate Expiration
345–027–0350
Changes Requiring an Amendment
345–027–0351
Review Processes for Requests for Amendment
345–027–0353
Changes Exempt from Requiring an Amendment
345–027–0355
Written Evaluations for Changes Not Requiring Amendment
345–027–0357
Amendment Determination Request
345–027–0359
Pre-Amendment Conference
345–027–0360
Preliminary Request for Amendment
345–027–0363
Determination of Completeness for a Request for Amendment
345–027–0365
Draft Proposed Order for a Request for Amendment
345–027–0367
Public Comment and Hearing on the Draft Proposed Order for Requests for Amendment Under Type A Review
345–027–0368
Public Written Comment on the Draft Proposed Order for Requests for Amendment Under Type B Review
345–027–0371
Proposed Order, Requests for Contested Case and Council’s Final Decision on Requests for Amendment Under Type A Review
345–027–0372
Proposed Order and Council’s Final Decision on Requests for Amendment Under Type B Review
345–027–0375
Scope of Council’s Review
345–027–0380
Type C Review Process for Pre-Operational Requests for Amendment
345–027–0385
Request for Amendment to Extend Construction Deadlines
345–027–0390
Request by Any Person for Amendment to Apply Later-Adopted Laws
345–027–0400
Request for Amendment to Transfer Ownership, Possession or Control of the Facility or the Certificate Holder
Last Updated

Jun. 8, 2021

Rule 345-027-0353’s source at or​.us