OAR 734-051-2030
Indentures of Access


(1)

General Provisions. Abutting property owners with a reservation of access must apply to the department to indenture or change the location, width or use restrictions of the reservation.

(2)

Criteria for Approval of Indenture of Access. The department may approve an application for indenture of access to a property abutting a state or local facility where all of the following criteria are met:

(a)

An applicant to indenture a reservation of access for a private approach must submit an application for state highway approach permit as set forth in OAR 734-051-3030 (Application Requirements for State Highway Private Approach) with its application for an indenture of access as set forth in this rule;

(b)

The applicant meets the requirements for issuance of a construction permit, as set forth in OAR 734-051-5020 (Issuance of Construction Permits);

(c)

The applicant agrees in writing to meet any mitigation measures, conditions, and terms placed on the construction permit and the permit to operate;

(d)

The property owner agrees to convey one or more existing reservations of access, including the reservation being indentured to the department and close any affected approaches; and

(e)

The region manager approves the application for indenture of access.

(3)

Mitigation. Approval of an indenture of a reservation of access for a public approach may require mitigation measures to ensure that the state transportation system can safely accommodate the traffic operations at the indentured location. Mitigation measures may include but are not limited to amendments to the comprehensive plan or transportation system plan, or modification to the public street system.

(4)

Process. The application procedures for indenture of access are:

(a)

A complete application for indenture of access to a state highway consists of a completed and signed standard state form, and the processing fee for indenture of access, except where the region manager, not a designee, waives the processing fee and documents in writing the reasons for the waiver;

(b)

The department shall not process an application for indenture of access that is incomplete;

(c)

Only the property owner or the owner’s designated agent shall submit an application for indenture of access;

(d)

Upon acceptance of an application for indenture of access, the department shall evaluate the application pursuant to division 51, ORS Chapter 374 (Control of Access to Public Highways), and any other applicable state statutes, administrative rules, and department manuals for evaluating and acting upon the application for an indenture of access; and

(e)

The region manager shall approve or deny the application for indenture of a reservation of access and shall notify the applicant.

Source: Rule 734-051-2030 — Indentures of Access, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=734-051-2030.

734‑051‑1010
Authority for Rules — General Provisions
734‑051‑1020
Purpose and Intent of Rules
734‑051‑1030
Administration of Rules
734‑051‑1040
Relationship to Local Jurisdiction Rules and Regulations
734‑051‑1050
Procedure to Obtain a Permit to Construct or Modify a Public Approach
734‑051‑1060
Delegation of Permit Authority to Local Jurisdiction
734‑051‑1065
Restriction of Turning Movements for Existing Private Approaches
734‑051‑1070
Definitions
734‑051‑2010
Rights of Access — General Provisions
734‑051‑2020
Grants of Access
734‑051‑2030
Indentures of Access
734‑051‑3010
Administration of Private Approaches — Permit for Private Approach
734‑051‑3015
Presumption of Written Permission for an Existing Private Connection
734‑051‑3020
Change of Use of a Private Connection
734‑051‑3030
Application Requirements for State Highway Private Approach
734‑051‑3040
Private Approach Permit Application Review, Approvals and Timelines
734‑051‑3050
Deviations from Approach Spacing, Sight Distance, and Channelization Standards for a Private Approach
734‑051‑3060
Pre-Decision Collaborative Discussion for Highway Approach Permit Applications
734‑051‑3070
Mitigation Measures
734‑051‑3080
Post-Decision Review Processes
734‑051‑3090
Post-Decision Collaborative Discussion
734‑051‑3100
Access Management Dispute Review Board
734‑051‑3110
Contested Case Hearing Process
734‑051‑4010
Access Management Standards for Approaches — General Provisions
734‑051‑4020
Standards and Criteria for Approval of Private Approaches
734‑051‑4030
Benefit to the State Highway System
734‑051‑4040
Temporary Approaches
734‑051‑4050
Special Use Approaches
734‑051‑5010
Approach Design and Construction — Design of Approaches
734‑051‑5020
Issuance of Construction Permits
734‑051‑5030
Construction of Approaches
734‑051‑5040
Effective Period of Construction Permits
734‑051‑5050
Responsibility for Costs of Construction of Approaches
734‑051‑5060
Liability, Insurance and Bonding Requirements
734‑051‑5070
Review Procedure for Modifying a Construction Permit
734‑051‑5080
Issuance of a Permit to Operate, Maintain and Use an Approach
734‑051‑5090
Maintenance of Approaches
734‑051‑5100
Effective Period of Permit to Operate, Maintain and Use an Approach
734‑051‑5110
Revocation of Permits and Removal of Approaches
734‑051‑5120
Access Management in Project Delivery
734‑051‑6010
Remedies in Closure of Approaches — Authority and Purpose of OAR 734-051-6010 through 734-051-6060
734‑051‑6020
Definitions
734‑051‑6030
Offer of Remedies
734‑051‑6040
Procedure for Resolving Claims
734‑051‑6050
Appraisals
734‑051‑6060
Conditions of Agreement
734‑051‑6070
Delegation
734‑051‑7010
Access Management in Highway Facility Plans
Last Updated

Jun. 8, 2021

Rule 734-051-2030’s source at or​.us