OAR 734-051-5020
Issuance of Construction Permits


(1)

General Requirements. The region manager shall issue a construction permit when construction plans, if required, and all other required documents are received and approved.

(2)

Procedure. Prior to issuing a construction permit the department will issue to the applicant construction specifications including all provisions, mitigation measures, conditions, and agreements that will become part of the construction permit. To receive a construction permit, the applicant must complete the following, pursuant to subsections (a) through (d) below, within sixty (60) days of the date of the department’s transmittal of the construction specifications:

(a)

Review and sign the construction specifications to confirm that the applicant understands and agrees to the specifications including all provisions, mitigation measures, conditions, and agreements that will become part of the construction permit; and

(b)

When the department determines that standard plans are not appropriate, an applicant must submit construction plans sealed by an engineer licensed in the state of Oregon within 60 days of notice of approval of an application to obtain a construction permit. The region manager determines the acceptability of submitted construction plans. If plans are not submitted within 60 days and no request for extension is received within that time, the approval of the application will be void; and

(c)

Return the signed construction specifications to the department; and

(d)

Submit proof of liability insurance and bond or deposit in lieu of bond as required by OAR 734-051-5060 (Liability, Insurance and Bonding Requirements).

(3)

Non-Compliance. If the applicant does not complete the actions required in section (2) of this rule within the 60-day timeframe, then the department will not issue a construction permit and all approvals associated with approach application will be revoked. The 60-day time frame may be extended if the permittee and the department agree in writing before the deadline pursuant to OAR 734-051-5040 (Effective Period of Construction Permits).

(4)

True and Complete Information. An applicant or permittee shall provide true and complete information, and if any required fact that is material to the assessment of the approach’s impact upon traffic safety, convenience or the legal or property rights of any person (including the State of Oregon) is false, incorrect or omitted, the region manager may:

(a)

Deny or revoke the construction permit; and

(b)

At the applicant’s or permittee’s expense require the applicant or permittee to:

(A)

Remove the approach and restore the area to a condition acceptable to the region manager;

(B)

Provide additional safeguards to protect the safety, convenience, and rights of the traveling public and persons (including the State), if such safeguards are adequate to achieve these purposes, as a condition of the continued validity of the permit to operate; and

(C)

Reconstruct or repair the approach.

(5)

Signed Permit Required. No work on highway right of way may begin until an applicant obtains a valid construction permit, approved and signed by the region manager.

Source: Rule 734-051-5020 — Issuance of Construction Permits, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=734-051-5020.

734‑051‑1010
Authority for Rules — General Provisions
734‑051‑1020
Purpose and Intent of Rules
734‑051‑1030
Administration of Rules
734‑051‑1040
Relationship to Local Jurisdiction Rules and Regulations
734‑051‑1050
Procedure to Obtain a Permit to Construct or Modify a Public Approach
734‑051‑1060
Delegation of Permit Authority to Local Jurisdiction
734‑051‑1065
Restriction of Turning Movements for Existing Private Approaches
734‑051‑1070
Definitions
734‑051‑2010
Rights of Access — General Provisions
734‑051‑2020
Grants of Access
734‑051‑2030
Indentures of Access
734‑051‑3010
Administration of Private Approaches — Permit for Private Approach
734‑051‑3015
Presumption of Written Permission for an Existing Private Connection
734‑051‑3020
Change of Use of a Private Connection
734‑051‑3030
Application Requirements for State Highway Private Approach
734‑051‑3040
Private Approach Permit Application Review, Approvals and Timelines
734‑051‑3050
Deviations from Approach Spacing, Sight Distance, and Channelization Standards for a Private Approach
734‑051‑3060
Pre-Decision Collaborative Discussion for Highway Approach Permit Applications
734‑051‑3070
Mitigation Measures
734‑051‑3080
Post-Decision Review Processes
734‑051‑3090
Post-Decision Collaborative Discussion
734‑051‑3100
Access Management Dispute Review Board
734‑051‑3110
Contested Case Hearing Process
734‑051‑4010
Access Management Standards for Approaches — General Provisions
734‑051‑4020
Standards and Criteria for Approval of Private Approaches
734‑051‑4030
Benefit to the State Highway System
734‑051‑4040
Temporary Approaches
734‑051‑4050
Special Use Approaches
734‑051‑5010
Approach Design and Construction — Design of Approaches
734‑051‑5020
Issuance of Construction Permits
734‑051‑5030
Construction of Approaches
734‑051‑5040
Effective Period of Construction Permits
734‑051‑5050
Responsibility for Costs of Construction of Approaches
734‑051‑5060
Liability, Insurance and Bonding Requirements
734‑051‑5070
Review Procedure for Modifying a Construction Permit
734‑051‑5080
Issuance of a Permit to Operate, Maintain and Use an Approach
734‑051‑5090
Maintenance of Approaches
734‑051‑5100
Effective Period of Permit to Operate, Maintain and Use an Approach
734‑051‑5110
Revocation of Permits and Removal of Approaches
734‑051‑5120
Access Management in Project Delivery
734‑051‑6010
Remedies in Closure of Approaches — Authority and Purpose of OAR 734-051-6010 through 734-051-6060
734‑051‑6020
Definitions
734‑051‑6030
Offer of Remedies
734‑051‑6040
Procedure for Resolving Claims
734‑051‑6050
Appraisals
734‑051‑6060
Conditions of Agreement
734‑051‑6070
Delegation
734‑051‑7010
Access Management in Highway Facility Plans
Last Updated

Jun. 8, 2021

Rule 734-051-5020’s source at or​.us