OAR 918-225-0609
Use of Minor Repair Permits
(1)
Only those minor repairs described in OAR 918-225-0612 (Scope of Work Allowed under Minor Repair Permit) may be performed under a minor repair permit.(2)
A minor repair permit authorizes work on a single boiler or pressure vessel. Multiple minor repairs may be performed under a minor repair permit provided that each minor repair is completed within the five day period that begins when the first minor repair is completed.(3)
All work performed under a minor repair permit must conform to the Oregon Boiler and Pressure Vessel Specialty Code.(4)
An individual performing work under a minor repair permit must:(a)
Hold the appropriate license, if required, under ORS 480.630 (Licensing of boiler contractors and persons installing, altering or repairing boilers or pressure vessels) and OAR 918-225-0691 (Boiler, Pressure Vessel and Pressure Piping Installation, Alteration or Repair Licensing Requirements) for the type of work performed;(b)
Fill out the information required on the minor repair permit; and(c)
Post the minor repair permit in a secure and visible location near the site of the repair.(5)
Within five business days of work being completed, the purchaser of the minor repair permit is responsible for ensuring that all work that was performed under the minor repair permit is recorded in the manner approved by the division.