Extension or Postponement of Date to Comply with Rules and Orders


(1)

Within 60 days of the date of service of a Commission order, any party may file a petition for extension or postponement of an effective date or of time to comply with the order.

(2)

The petition must specify reasons for the requested extension or postponement.