Utility Regulation Generally

ORS 757.050
Authority of commission to order extension of service to unserved areas


The Public Utility Commission has power to require any public utility, after a public hearing of all parties interested, to extend its line, plant or system into, and to render service to, a locality not already served when the existing public convenience and necessity requires such extension and service. However, no such extension of service shall be required until the public utility has been granted such reasonable franchises as may be necessary for the extension of service, and unless the conditions are such as to reasonably justify the necessary investment by the public utility in extending its line, plant or system into such locality and furnishing such service. [Amended by 1971 c.655 §67]
Chapter 757

Notes of Decisions

Under regulatory scheme, Public Utility Commissioner has authority to promulgate rule limiting telephone company's liability for directory listing errors or omissions. Garrison v. Pacific NW Bell, 45 Or App 523, 608 P2d 1206 (1980)

Refund is proper exercise of Public Utility Commission's general powers if refund (1) is based only on information in existence at time of rate order for which refund is being made; (2) is not based on evaluation of public utility's actual expenses or revenues; and (3) is not effectuated by offsetting future rates. Gearhart v. Public Utility Commission, 255 Or App 58, 299 P3d 533 (2013), aff'd 356 Or 216, 339 P3d 904 (2014)

Atty. Gen. Opinions

Authority of Governor and Public Utility Commissioner to enter into binding agreements with respect to uniform curtailment plans, (1977) Vol 38, p 861


Source

Last accessed
Jun. 26, 2021