ORS 758.240
Contract with utility for conversion


(1)

When a public authority in accordance with ORS 758.230 (Assessment procedure) determines that a conversion shall be made, it may contract with the utilities supplying electric or communication service within the underground assessment district to perform the conversion. A contract shall provide:

(a)

A description of the electric and communication facilities to be converted;

(b)

That plans and specifications for such conversion shall be supplied or approved by the affected utility;

(c)

The time and manner in which underground electric and communication facilities will be installed and overhead electric and communication facilities will be removed;

(d)

The estimated cost of converting overhead facilities located on public lands and right of way to underground facilities;

(e)

The estimated cost of converting related utility service facilities located on privately owned lots and parcels;

(f)

The time and manner of making payments and the source of funds for such payments; and

(g)

That upon completion of the work of conversion, the utility performing the conversion shall have legal title to the electric or communication facilities, which shall thereafter constitute a part of a system of the utility and be used, operated, maintained and managed by it as part of its system.

(2)

Upon approval and execution of the conversion contracts by the utilities and public authority, the public authority shall direct the utilities owning overhead electric or communication facilities within the district to convert such facilities as required by the contract. [1969 c.385 §7]

Source: Section 758.240 — Contract with utility for conversion, https://www.­oregonlegislature.­gov/bills_laws/ors/ors758.­html.

758.010
Authority to construct lines and facilities
758.012
Notice of intent to build transmission line to consumer-owned utilities and public utilities
758.013
Operator of electric power line to provide Public Utility Commission with safety information
758.015
Certificate of public convenience and necessity
758.017
Appeal of grant or denial of certificate of public convenience and necessity for transmission lines subject to Energy Facility Siting Council approval
758.020
Joint occupancy of poles
758.025
Relocation of utilities in highway right of way
758.035
Commission’s power to enforce joint use of facilities
758.120
Electric easement in provision of broadband services
758.125
Duties and rights not altered by ORS 758.120
758.130
Requirements for electric cooperative in provision of broadband services
758.210
Policy
758.215
Definitions for ORS 758.210 to 758.270
758.220
Authority for conversion to underground facilities
758.225
Petition, ordinance or resolution for conversion
758.230
Assessment procedure
758.235
Applicability of local improvement laws
758.240
Contract with utility for conversion
758.245
Payment of costs for conversion
758.250
Conversion of facilities on private lands
758.255
Discontinuance of utility service for noncompliance with conversion provisions
758.260
Competitive bidding for utility conversion
758.265
Overhead facilities in assessment district after conversion
758.270
Effect of ORS 758.210 to 758.270 on existing laws and rights
758.280
Definitions for ORS 758.280 to 758.286
758.282
Immunity of electric utility for pruning or removing vegetation in certain cases
758.284
Immunity of electric utility for pruning or removing vegetation in other cases
758.286
Immunity not applicable to liability for cost of abating fires
758.300
Definitions for ORS 758.300 to 758.320
758.302
Application for exclusive service territory
758.305
Exclusive service territories
758.310
Assignment or transfer of rights in exclusive service territory
758.315
Water utility service provided by persons not designated by commission
758.320
Application of ORS 758.300 to 758.320 to cities
758.400
Definitions for ORS 758.015 and 758.400 to 758.475
758.405
Purpose of ORS 758.400 to 758.475
758.410
Contracts for allocation of territories and customers
758.415
Enforceability of contract approved by commission
758.420
Filing of contract
758.425
Order of commission on contract
758.430
Amendment of contract
758.435
Application for allocation of territory
758.440
Order of commission on application
758.445
Judicial review of order on application
758.450
Contract required for allocation of territory
758.455
Investigation by commission respecting contracts or applications
758.460
Assignment or transfer of rights acquired by allocation
758.465
Enforcement procedure
758.470
Application to cities, municipalities and cooperatives of ORS 758.400 to 758.475
758.475
Fees
758.480
Assumption of obligations arising out of Trojan Nuclear Plant
758.505
Definitions for ORS 758.505 to 758.555
758.515
Legislative findings
758.525
Avoided cost schedules
758.535
Criteria for qualifying facility
758.545
Electric utility required to make good faith effort to transmit energy
758.552
Ownership of renewable energy certificates for energy generated by qualifying facility
758.555
Effect of energy sales on qualifying facility
Green check means up to date. Up to date