Oregon Utility Rights of Way and Territory Allocation; Cogeneration
ORS 758.430
Amendment of contract; approval of commission


Any contract that has been approved as provided in ORS 758.400 (Definitions for ORS 758.015 and 758.400 to 758.475) to 758.475 (Fees) may be subsequently amended by the parties thereto, but any such amendatory agreement shall be filed with the Public Utility Commission and shall thereafter be approved or disapproved by the commission in the manner provided in ORS 758.420 (Filing of contract) and 758.425 (Order of commission on contract). However, no hearing is required if all affected customers approve the amendatory agreement. An amendatory agreement may be enforced in the manner provided in ORS 758.465 (Enforcement procedure). [Formerly 757.635; 1983 c.540 §5]