ORS 758.435
Application for allocation of territory

  • hearing on application
  • notice

(1)

Any person providing a utility service in a territory that is not served by another person providing a similar utility service may file an application with the Public Utility Commission for an order allocating such territory to the person providing the utility service. The application may include any adjacent area when it is more economical and feasible to serve the adjacent area by an extension of the applicant’s existing facilities than by an extension of the facilities of another person. An application must include a copy of the notice of the filing to be given to all customers of record, and the applicant shall, within 30 days after filing an application under this section, give notice of the filing in the manner provided by subsection (4) of this section.

(2)

Within 30 days after the filing of an application under this section, the commission shall give notice of the filing to all providers of similar utility services in the areas adjacent to the area covered by the application.

(3)

If the commission chooses, or if a customer requests a hearing on the matter within 30 days of the notice, the commission shall hold a hearing by telephone, video conference or other electronic means of communication or in person. The commission shall give notice of the hearing in the manner provided by subsection (4) of this section within 30 days of the request. The notice shall set the date and place of hearing. The hearing shall be held at a place within or conveniently accessible to the territory covered by the application.

(4)

Intentionally left blank —Ed.

(a)

A notice given pursuant to this subsection shall be given:

(A)

By mail or electronic mail to all customers of record in the area covered by the application;

(B)

By press release to news media local to the area covered by the application; and

(C)

By publication in one or more newspapers of general circulation in the area covered by the application at least once weekly for two successive weeks.

(b)

The notice must include a description of the area covered by the application and the general rate impact to existing customers.

(5)

Territory within the limits of a city, as fixed on May 31, 1961, shall not be deemed to be served exclusively by any person, if such city is, on such date, served by more than one person having necessary municipal or franchise authority to serve within the entire city. [Formerly 757.640; 1985 c.633 §1; 2023 c.53 §6]

Source: Section 758.435 — Application for allocation of territory; hearing on application; notice, https://www.­oregonlegislature.­gov/bills_laws/ors/ors758.­html (accessed May 26, 2025).

Notes of Decisions

Public Utility Commission allocation of exclusive service area is entitled to state-action immunity from federal antitrust law. Columbia River PUD v. Portland General Electric, 40 F. Supp. 2d 1152 (D. Or. 1999)

758.010
Authority to construct lines and facilities
758.012
Notice of intent to build transmission line to consumer-owned utilities and public utilities
758.013
Operator of electric power line to provide Public Utility Commission with safety information
758.015
Certificate of public convenience and necessity
758.017
Appeal of grant or denial of certificate of public convenience and necessity for transmission lines subject to Energy Facility Siting Council approval
758.020
Joint occupancy of poles
758.025
Relocation of utilities in highway right of way
758.035
Commission’s power to enforce joint use of facilities
758.120
Electric easement in provision of broadband services
758.125
Duties and rights not altered by ORS 758.120
758.130
Requirements for electric cooperative in provision of broadband services
758.210
Policy
758.215
Definitions for ORS 758.210 to 758.270
758.220
Authority for conversion to underground facilities
758.225
Petition, ordinance or resolution for conversion
758.230
Assessment procedure
758.235
Applicability of local improvement laws
758.240
Contract with utility for conversion
758.245
Payment of costs for conversion
758.250
Conversion of facilities on private lands
758.255
Discontinuance of utility service for noncompliance with conversion provisions
758.260
Competitive bidding for utility conversion
758.265
Overhead facilities in assessment district after conversion
758.270
Effect of ORS 758.210 to 758.270 on existing laws and rights
758.280
Definitions for ORS 758.280 to 758.286
758.282
Immunity of electric utility for pruning or removing vegetation in certain cases
758.284
Immunity of electric utility for pruning or removing vegetation in other cases
758.286
Immunity not applicable to liability for cost of abating fires
758.300
Definitions for ORS 758.300 to 758.320
758.302
Application for exclusive service territory
758.305
Exclusive service territories
758.310
Assignment or transfer of rights in exclusive service territory
758.315
Water utility service provided by persons not designated by commission
758.320
Application of ORS 758.300 to 758.320 to cities
758.400
Definitions for ORS 758.015 and 758.400 to 758.475
758.405
Purpose of ORS 758.400 to 758.475
758.410
Contracts for allocation of territories and customers
758.415
Enforceability of contract approved by commission
758.420
Filing of contract
758.425
Order of commission on contract
758.430
Amendment of contract
758.435
Application for allocation of territory
758.440
Order of commission on application
758.445
Judicial review of order on application
758.450
Contract required for allocation of territory
758.455
Investigation by commission respecting contracts or applications
758.460
Assignment or transfer of rights acquired by allocation
758.465
Enforcement procedure
758.470
Application to cities, municipalities and cooperatives of ORS 758.400 to 758.475
758.475
Fees
758.480
Assumption of obligations arising out of Trojan Nuclear Plant
758.505
Definitions for ORS 758.505 to 758.555
758.515
Legislative findings
758.525
Avoided cost schedules
758.535
Criteria for qualifying facility
758.545
Electric utility required to make good faith effort to transmit energy
758.552
Ownership of renewable energy certificates for energy generated by qualifying facility
758.555
Effect of energy sales on qualifying facility

Current through early 2026